Pearie Law 2 (14.4 MW wind farm)

Pearie Law 2 is a 14.4 MW wind farm project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 December 2021, not yet built; the record was last updated on 20 May 2024. REPD records the planning permission as expiring on 22 December 2024, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.4 MWwind farm
approved, not builtmay be out of datestatus in REPD
20 May 2024record last updated
West Lothiancouncil area

REPD records the planning permission as expiring on 22 December 2024, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
8 February 2021Application submitted
22 December 2021Planning permission granted
22 December 2024Permission expired

Project details

Technology
wind farm
Capacity
14.4 MW
Status (REPD)
approved, not built
Record last updated
20 May 2024
Operator or applicant
Wind Estate (UK) Ltd
Planning authority
West Lothian
Planning application reference
0124/FUL/21
Turbines
4
Turbine height
180 m
Address (REPD)
Pearie Law West Calder West Lothian
Council area (by location)
West Lothian
Time to decision
45 weeks
Contracts for Difference
AR5
Name in REPD
Pearie Law 2 - Wind turbines
REPD reference
8847

Who decides

ApplicationsWest LothianUK
Decided applications (solar, wind, battery)4110,236
Refused5 (12%)19%
Solar refused1 of 1712%
Onshore wind refused4 of 1545%
Battery storage refused0 of 916%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pearie Law Wind Farmwind farm19.2operational1.3
Pates Hillwind farm14operational2.4
PATES HILL WIND FARM Extensionwind farm6application withdrawn3.2
Woolfords Farm - Onshore Wind Turbineswind farm19.8approved, not built3.5
Longhill Burn Wind Farmwind farm45.6under construction3.5
Harburnhead Wind Farmwind farm51.7operational3.6
Camilty Plantation Wind Farmwind farm25.8approved, not built4.5
Fauch Hillwind farm48refused on appeal5.8
Heathland Wind Farmwind farm80approved, not built6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8278, -3.5783).