Fauch Hill (48 MW wind farm)

Fauch Hill is a 48 MW wind farm project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 13 June 2018; the record was last updated on 28 June 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWwind farm
refused on appealstatus in REPD
28 June 2018record last updated
West Lothiancouncil area

Planning timeline

DateStage
3 April 2017Application submitted
20 December 2017Refused by the planning authority
16 March 2018Appeal lodged
13 June 2018Appeal refused

Project details

Technology
wind farm
Capacity
48 MW
Status (REPD)
refused on appeal
Record last updated
28 June 2018
Operator or applicant
Fauch Hill Sustainable Energy
Planning authority
West Lothian
Planning application reference
LIVE/0235/FUL/17
Appeal reference
PPA-400-2084
Turbines
12
Turbine height
125 m
Address (REPD)
Fauch Hill, West Colzium, Crosswoodburn, West Calder, Lothian
Council area (by location)
West Lothian
Time to decision
37 weeks
REPD reference
6291

Who decides

ApplicationsWest LothianUK
Decided applications (solar, wind, battery)4110,236
Refused5 (12%)19%
Solar refused1 of 1712%
Onshore wind refused4 of 1545%
Battery storage refused0 of 916%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Camilty Plantation Wind Farmwind farm25.8approved, not built1.9
Harburnhead Wind Farmwind farm51.7operational2.3
Fauch Hill Wind Farmwind farm69refused2.4
Harrow's Lawwind farm39refused on appeal4.4
Pearie Law Wind Farmwind farm19.2operational4.6
Pearie Law 2wind farm14.4approved, not built5.8
Muirhallwind farm12.3operational6.8
Woolfords Farm - Onshore Wind Turbineswind farm19.8approved, not built6.9
Pates Hillwind farm14operational7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8024, -3.4967).