Fauch Hill Wind Farm (69 MW)

Fauch Hill Wind Farm is a 69 MW wind farm project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 July 2014; the record was last updated on 30 July 2014. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

69 MWwind farm
refusedstatus in REPD
30 July 2014record last updated
West Lothiancouncil area

Planning timeline

DateStage
23 February 2012Application submitted
8 July 2014Refused by the planning authority

Project details

Technology
wind farm
Capacity
69 MW
Status (REPD)
refused
Record last updated
30 July 2014
Operator or applicant
European Forest Resources Group
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
23
Address (REPD)
Colzium Hill Farm, West Lothian
Council area (by location)
West Lothian
Time to decision
124 weeks
REPD reference
4161

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Fauch Hillwind farm48refused on appeal2.4
Camilty Plantation Wind Farmwind farm25.8approved, not built4.0
Harburnhead Wind Farmwind farm51.7operational4.7
Harrow's Lawwind farm39refused on appeal5.0
Pearie Law Wind Farmwind farm19.2operational6.9
Pearie Law 2wind farm14.4approved, not built8.2
Muirhallwind farm12.3operational8.2
Woolfords Farm - Onshore Wind Turbineswind farm19.8approved, not built9.0
Leyden Roadsolar farm40application submitted9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7928, -3.4628).