Black Law Extension - 1b (15 MW wind farm)

Black Law Extension - 1b is a 15 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 February 2016; the record was last updated on 16 May 2016. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
operationalstatus in REPD
16 May 2016record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
10 May 2011Application submitted
17 June 2015Section 36 consent granted (Scottish Ministers)
18 August 2015Construction started
18 February 2016Operational

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
16 May 2016
Operator or applicant
Scottish Power Renewables
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
5
Address (REPD)
Black Law, Climpy
Council area (by location)
South Lanarkshire
Time to decision
214 weeks
REPD reference
4580

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Black Law Extension - 1awind farm48.4operational<0.1
Black Lawwind farm124operational<0.1
Damside Wind Farmwind farm20refused3.9
Gladsmuir Hills Wind Farmwind farm41approved, not built4.6
Hill Rig Community Wind Farmwind farm28refused4.9
Watsonhead Wind Farmwind farm8.4operational5.3
Tormywheel Wind Farm Extensionwind farm5approved, not built6.6
Tormywheelwind farm30.8operational7.4
Hartwood Windfarmwind farm21permission expired7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7622, -3.7626).