Hartwood Windfarm (21 MW)

Hartwood Windfarm is a 21 MW wind farm project in North Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 24 November 2022; the record was last updated on 22 April 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWwind farm
permission expiredstatus in REPD
22 April 2020record last updated
North Lanarkshirecouncil area

Planning timeline

DateStage
25 August 2014Application submitted
6 December 2016Refused by the planning authority
31 January 2017Appeal lodged
24 November 2017Planning permission granted
24 November 2017Appeal allowed
24 November 2022Permission expired

Project details

Technology
wind farm
Capacity
21 MW
Status (REPD)
permission expired
Record last updated
22 April 2020
Operator or applicant
ABO Wind UK
Planning authority
North Lanarkshire
Planning application reference
14/01699/FUL
Appeal reference
PPA-320-2113
Turbines
7
Turbine height
127 m
Address (REPD)
Land At Murdostoun Forrest & Home Farm, Hartwood, Shotts
Council area (by location)
North Lanarkshire
Time to decision
170 weeks
REPD reference
6312

Who decides

ApplicationsNorth LanarkshireUK
Decided applications (solar, wind, battery)3810,236
Refused9 (24%)19%
Solar refused0 of 1412%
Onshore wind refused8 of 2045%
Battery storage refused1 of 416%
Median time from submission to decision34.4 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hartwoodwind farm30application withdrawn1.4
Fernishaw Solar Farm & Battery Energy Storage Facilitysolar farm75approved, not built2.6
Salsburghwind farm24application withdrawn3.3
Damside Wind Farmwind farm20refused3.7
Dewshill Wind Farmwind farm9approved, not built4.2
Watsonhead Wind Farmwind farm8.4operational4.2
Brownhill Farmwind farm8.4under construction5.0
West Benhar wind farmwind farm27.2operational5.4
North Lanrigg Energy Storagebattery storage200approved, not built5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8126, -3.84).