Torrance Wind Farm Extension 2 (26.4 MW)

Torrance Wind Farm Extension 2 is a 26.4 MW wind farm project in North Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 7 March 2025; the record was last updated on 11 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26.4 MWwind farm
refusedstatus in REPD
11 March 2025record last updated
North Lanarkshirecouncil area

Planning timeline

DateStage
29 March 2023Application submitted
7 March 2025Refused by the planning authority

Project details

Technology
wind farm
Capacity
26.4 MW
Status (REPD)
refused
Record last updated
11 March 2025
Operator or applicant
Infinergy
Planning authority
North Lanarkshire
Planning application reference
23/00256/FUL
Turbines
4
Turbine height
200 m
Address (REPD)
Westcraigs Road Harthill
Council area (by location)
North Lanarkshire
Time to decision
101 weeks
REPD reference
11007

The scheme also includes battery storage, recorded separately in REPD (refused).

Who decides

ApplicationsNorth LanarkshireUK
Decided applications (solar, wind, battery)3810,236
Refused9 (24%)19%
Solar refused0 of 1412%
Onshore wind refused8 of 2045%
Battery storage refused1 of 416%
Median time from submission to decision34.4 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Torrance Farmwind farm9operational1.1
Benhar Windfarmwind farm15refused on appeal1.7
Torrance Farm Wind Park Extensionwind farm5.7operational1.7
West Benhar Road, Eastfield, Harthillwind farm20application submitted2.5
Shotts wind farmwind farm18refused on appeal2.7
Heights Road, Blackridge - Woodend Wind Farmwind farm19.8application submitted2.8
Brownhill Farmwind farm8.4under construction3.0
West Benhar wind farmwind farm27.2operational3.0
Starryshaw Wind Farmwind farm12refused3.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8618, -3.749).