Energy Projects Near You

Heights Road, Blackridge - Woodend Wind Farm (19.8 MW)

Heights Road, Blackridge - Woodend Wind Farm is a 19.8 MW wind farm project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 16 June 2023, no decision recorded; the record was last updated on 4 July 2023. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.8 MWwind farm
application submittedmay be out of datestatus in REPD
4 July 2023record last updated
West Lothiancouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
16 June 2023Application submitted

Project details

Technology
wind farm
Capacity
19.8 MW
Status (REPD)
application submitted
Record last updated
4 July 2023
Operator or applicant
Wind Estate (UK) Ltd
Planning authority
West Lothian
Planning application reference
0434/FUL/23
Turbines
3
Turbine height
180 m
Address (REPD)
Heights Road, Blackridge, Bathgate
Council area (by location)
West Lothian
REPD reference
12422

Who decides

ApplicationsWest LothianUK
Decided applications (solar, wind, battery)4110,236
Refused5 (12%)19%
Solar refused1 of 1712%
Onshore wind refused4 of 1545%
Battery storage refused0 of 916%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Torrance Farm Wind Park Extensionwind farm5.7operational1.5
Drumduff Wind Farm Extensionwind farm15approved, not built1.7
Torrance Farmwind farm9operational1.9
Drumduffwind farm8.5operational2.3
Torrance Wind Farm Extension 2wind farm26.4refused2.8
Burnheadwind farm26operational3.0
Forrestfield Wind Farmwind farm13.2application submitted3.5
Benhar Windfarmwind farm15refused on appeal4.0
West Benhar Road, Eastfield, Harthillwind farm20application submitted4.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8856, -3.7641).