Drumduff Wind Farm Extension (15 MW)
Drumduff Wind Farm Extension is a 15 MW wind farm project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 April 2024, not yet built; the record was last updated on 10 February 2026.
15 MWwind farm
approved, not builtstatus in REPD
10 February 2026record last updated
West Lothiancouncil area
Planning timeline
| Date | Stage |
|---|---|
| 16 June 2023 | Application submitted |
| 25 April 2024 | Planning permission granted |
| 25 April 2027 | Permission due to expire (unless work starts) |
Project details
- Technology
- wind farm
- Capacity
- 15 MW
- Status (REPD)
- approved, not built
- Record last updated
- 10 February 2026
- Operator or applicant
- Green Power (International) Limited
- Planning authority
- West Lothian
- Planning application reference
- 0504/FUL/23
- Turbines
- 3
- Turbine height
- 150 m
- Address (REPD)
- S/O Drumduff Wind Farm, Blackridge
- Council area (by location)
- West Lothian
- Time to decision
- 45 weeks
- Contracts for Difference
- AR7a
- REPD reference
- 13132
Who decides
| Applications | West Lothian | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 41 | 10,236 |
| Refused | 5 (12%) | 19% |
| Solar refused | 1 of 17 | 12% |
| Onshore wind refused | 4 of 15 | 45% |
| Battery storage refused | 0 of 9 | 16% |
| Median time from submission to decision | 17.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Drumduff | wind farm | 8.5 | operational | 0.6 |
| Burnhead | wind farm | 26 | operational | 1.4 |
| Heights Road, Blackridge - Woodend Wind Farm | wind farm | 19.8 | application submitted | 1.7 |
| Torrance Farm Wind Park Extension | wind farm | 5.7 | operational | 3.1 |
| Torrance Farm | wind farm | 9 | operational | 3.6 |
| Easter Drumclair Wood | wind farm | 6 | approved, not built | 3.6 |
| Forrestfield Wind Farm | wind farm | 13.2 | application submitted | 3.8 |
| Torrance Wind Farm Extension 2 | wind farm | 26.4 | refused | 4.5 |
| Nether braco Farm | wind farm | 21 | application withdrawn | 4.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8999, -3.7739).