Greengairs East Wind Farm (24 MW)

Greengairs East Wind Farm is a 24 MW wind farm project in North Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 August 2023; the record was last updated on 5 September 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWwind farm
operationalstatus in REPD
5 September 2023record last updated
North Lanarkshirecouncil area

Planning timeline

DateStage
29 June 2012Application submitted
13 February 2019Planning permission granted
1 May 2022Construction started
25 August 2023Operational

Project details

Technology
wind farm
Capacity
24 MW
Status (REPD)
operational
Record last updated
5 September 2023
Operator or applicant
Muirhall Energy
Planning authority
North Lanarkshire
Planning application reference
12/00602/FUL
Turbines
8
Turbine height
125 m
Address (REPD)
N/o Easterton, Airdrie Road Caldercruix, Airdrie, Lanarkshire, ML6
Council area (by location)
North Lanarkshire
Time to decision
346 weeks
REPD reference
4213

Who decides

ApplicationsNorth LanarkshireUK
Decided applications (solar, wind, battery)3810,236
Refused9 (24%)19%
Solar refused0 of 1412%
Onshore wind refused8 of 2045%
Battery storage refused1 of 416%
Median time from submission to decision34.4 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Greengairs Wind Farmwind farm17.5permission expired1.1
Nether braco Farmwind farm21application withdrawn4.5
Bracco / Black Hillwind farm72.5application withdrawn4.7
Forrestfield Wind Farmwind farm13.2application submitted6.4
Easter Drumclair Woodwind farm6approved, not built6.7
Burnbank Street, Greenhillbattery storage30approved, not built7.4
Locks Street, Coatdyke Battery Energy Storage Systemsbattery storage45application submitted7.4
North Lanrigg Energy Storagebattery storage200approved, not built7.4
Dewshill Wind Farmwind farm9approved, not built7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9011, -3.912).