Solar, wind and battery projects near Cumbernauld (G67)
15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of G67 (North Lanarkshire): 3 are waiting for a planning decision, 5 approved but not yet running, 2 operational. The largest live scheme is Locks Street, Coatdyke Battery Energy Storage Systems (45 MW battery storage, application submitted on 15 September 2025, no decision recorded), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of G67
Projects of 1 MW and more (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Glenhove Pumping Station, Glenhove Roadbattery storage | battery storage | 3.1 | application submitted | May 2026 | — | — | North Lanarkshire | 2.4 |
| Glenhove Pumping Station, Glenhove Roadsolar farm | solar farm | 1.9 | application submitted | May 2026 | — | — | North Lanarkshire | 2.4 |
| Glenhead Farm Lower Solar Arraysolar farm | solar farm | 4.1 | permission expiredupdated Jul 2020 | Oct 2015 | granted Jul 2016 | Jul 2020 | North Lanarkshire | 4.3 |
| Greengairs Wind Farmwind farm | wind farm | 17.5 | permission expiredupdated Sep 2020 | Feb 2007 | granted Aug 2008 | Sep 2020 | North Lanarkshire | 5.8 |
| Glenhead Farm (Upper)solar farm | solar farm | 5 | permission expiredupdated Jul 2020 | Oct 2015 | granted Jul 2016 | Jul 2020 | North Lanarkshire | 6.1 |
| Berryhill Farm Solar Arraysolar farm | solar farm | 4.8 | permission expiredupdated Jul 2020 | Oct 2015 | granted Jul 2016 | Jul 2020 | North Lanarkshire | 6.2 |
| Greendykesidewind farm | wind farm | 4 | operationalupdated Oct 2009 | Sep 2004 | granted May 2005 | Oct 2009 | North Lanarkshire | 6.5 |
| A Bartlett and Sonswind turbine | wind turbine | 1 | approved, not builtupdated Aug 2025 | Nov 2023 | granted Jul 2025 | Aug 2025 | North Lanarkshire | 6.7 |
| Greengairs East Wind Farmwind farm | wind farm | 24 | operationalupdated Sep 2023 | Jun 2012 | granted Feb 2019 | Sep 2023 | North Lanarkshire | 6.9 |
| Dalmacoulter Landfill, Dalmacoulter Road Solar Farmsolar farm | solar farm | 1 | approved, not builtupdated Jun 2026 | Aug 2025 | granted Apr 2026 | Jun 2026 | North Lanarkshire | 7.5 |
| Greenhill Farmwind turbine | wind turbine | 2 | application withdrawnupdated Oct 2017 | Jun 2017 | — | Oct 2017 | Falkirk | 7.9 |
| Burnbank Street, Greenhillbattery storage | battery storage | 30 | approved, not builtupdated Sep 2024 | Feb 2024 | granted Aug 2024 | Sep 2024 | North Lanarkshire | 8.8 |
| Wester Moffat Farm, Towers Roadsolar farm | solar farm | 2 | approved, not builtupdated Mar 2026 | Oct 2025 | granted Jan 2026 | Mar 2026 | North Lanarkshire | 9.0 |
| Locks Street, Coatdyke Battery Energy Storage Systemsbattery storage | battery storage | 45 | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 | North Lanarkshire | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (1)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Greens Road, Blairlinnrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2024 | Apr 2024 | granted May 2024 | May 2024 | North Lanarkshire | 1.8 |
Distance from the average position of the G67 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 1 | 2 | 0 | 0 | 4.9 |
| Rooftop solar | 1 | 0 | 1 | 0 | 0 | 0.4 |
| Wind farm | 3 | 0 | 0 | 2 | 0 | 0 |
| Wind turbine | 2 | 0 | 1 | 0 | 0 | 1 |
| Battery storage | 3 | 2 | 1 | 0 | 0 | 78.1 |
MW in pipeline: pending, approved and under-construction capacity.
How North Lanarkshire decides solar, wind and battery applications
| Applications | North Lanarkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 38 | 10,236 |
| Refused | 9 (24%) | 19% |
| Solar refused | 0 of 14 | 12% |
| Onshore wind refused | 8 of 20 | 45% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 34.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 2 | — |
All projects in North Lanarkshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.