Energy Projects Near You

Glenhead Farm (Upper) (5 MW solar farm)

Glenhead Farm (Upper) is a 5 MW solar farm project in North Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 6 July 2021; the record was last updated on 28 July 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
28 July 2020record last updated
North Lanarkshirecouncil area

Planning timeline

DateStage
21 October 2015Application submitted
6 July 2016Planning permission granted
6 July 2021Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
28 July 2020
Operator or applicant
Environmental Energy Investments
Planning authority
North Lanarkshire
Planning application reference
15/02233/FUL
Site area
9.1 ha
Address (REPD)
Glenhead Farm, High Banton Road, Kilsyth, Glasgow, Strathclyde, Scotland
Council area (by location)
North Lanarkshire
Time to decision
37 weeks
REPD reference
5909

Who decides

ApplicationsNorth LanarkshireUK
Decided applications (solar, wind, battery)3810,236
Refused9 (24%)19%
Solar refused0 of 1412%
Onshore wind refused8 of 2045%
Battery storage refused1 of 416%
Median time from submission to decision34.4 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Craigannet Wind Farmwind farm15refused on appeal5.3
Rullie Community Windfarmwind farm25application withdrawn6.5
Craigengeltwind farm20operational6.6
Carron Valley (Cairnoch Hill) Wind Farmwind farm45refused on appeal7.1
Muirparkwind farm33refused7.7
Earlsburnwind farm37.5operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9967, -4.0258).