Muirpark (33 MW wind farm)
Muirpark is a 33 MW wind farm project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 3 May 2012; the record was last updated on 3 May 2012.
33 MWwind farm
refusedstatus in REPD
3 May 2012record last updated
Stirlingcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 1 March 2009 | Application submitted |
| 3 May 2012 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 33 MW
- Status (REPD)
- refused
- Record last updated
- 3 May 2012
- Operator or applicant
- Airtricity Developments
- Planning authority
- Stirling
- Planning application reference
- 09/00170/FULL
- Turbines
- 11
- Address (REPD)
- Muirpark Farm, Stirling
- Council area (by location)
- Stirling
- Time to decision
- 166 weeks
- REPD reference
- 3959
Who decides
| Applications | Stirling | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 23 | 10,236 |
| Refused | 7 (30%) | 19% |
| Solar refused | 0 of 7 | 12% |
| Onshore wind refused | 6 of 11 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 30.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Craigengelt | wind farm | 20 | operational | 1.9 |
| Craigannet Wind Farm | wind farm | 15 | refused on appeal | 3.8 |
| Earlsburn | wind farm | 37.5 | operational | 4.3 |
| Rullie Community Windfarm | wind farm | 25 | application withdrawn | 4.8 |
| Carron Valley (Cairnoch Hill) Wind Farm | wind farm | 45 | refused on appeal | 5.2 |
| Earlsburn Wind Farm Extension | wind farm | 34 | approved, not built | 6.2 |
| Earlsburn North (Kingsburn) Wind Farm | wind farm | 22.5 | operational | 6.5 |
| Craigton and Spittalhill Wind Farm | wind farm | 21 | permission expired | 7.5 |
| Shelloch Wind Farm | wind farm | 24 | approved, not built | 7.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0664, -4.027).