Shelloch Wind Farm (24 MW)

Shelloch Wind Farm is a 24 MW wind farm project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 February 2022, not yet built; the record was last updated on 26 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWwind farm
approved, not builtstatus in REPD
26 August 2025record last updated
Stirlingcouncil area

Planning timeline

DateStage
5 January 2021Application submitted
11 February 2022Planning permission granted
11 February 2027Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
24 MW
Status (REPD)
approved, not built
Record last updated
26 August 2025
Operator or applicant
Force 9 Energy Partners Llp
Planning authority
Stirling
Planning application reference
20/00840/FUL
Turbines
5
Turbine height
170 m
Address (REPD)
Shelloch Wind Farm 2 Kilometres North W/O Wester Cringate, Polmaise Road To Carron Reservoir
Council area (by location)
Stirling
Time to decision
57 weeks
REPD reference
7886

Who decides

ApplicationsStirlingUK
Decided applications (solar, wind, battery)2310,236
Refused7 (30%)19%
Solar refused0 of 712%
Onshore wind refused6 of 1145%
Battery storage refused1 of 516%
Median time from submission to decision30.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Earlsburn Wind Farm Extensionwind farm34approved, not built1.7
Unit 15, Borrowmeadow Roadbattery storage19abandoned2.3
Easter Cringate Cottage, Polmaise Roadwind farm30application submitted2.6
Farm at Lower Polmaisesolar farm5permission expired3.4
Manor Powissolar farm5application withdrawn4.4
Glenside Farmbattery storage400approved, not built5.5
Rullie Community Windfarmwind farm25application withdrawn6.6
Muirparkwind farm33refused7.6
Tod Hill Farm Wind Turbineswind farm12operational7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.097, -3.917).