Shelloch Wind Farm (24 MW)
Shelloch Wind Farm is a 24 MW wind farm project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 February 2022, not yet built; the record was last updated on 26 August 2025.
24 MWwind farm
approved, not builtstatus in REPD
26 August 2025record last updated
Stirlingcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 5 January 2021 | Application submitted |
| 11 February 2022 | Planning permission granted |
| 11 February 2027 | Permission due to expire (unless work starts) |
Project details
- Technology
- wind farm
- Capacity
- 24 MW
- Status (REPD)
- approved, not built
- Record last updated
- 26 August 2025
- Operator or applicant
- Force 9 Energy Partners Llp
- Planning authority
- Stirling
- Planning application reference
- 20/00840/FUL
- Turbines
- 5
- Turbine height
- 170 m
- Address (REPD)
- Shelloch Wind Farm 2 Kilometres North W/O Wester Cringate, Polmaise Road To Carron Reservoir
- Council area (by location)
- Stirling
- Time to decision
- 57 weeks
- REPD reference
- 7886
Who decides
| Applications | Stirling | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 23 | 10,236 |
| Refused | 7 (30%) | 19% |
| Solar refused | 0 of 7 | 12% |
| Onshore wind refused | 6 of 11 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 30.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Earlsburn Wind Farm Extension | wind farm | 34 | approved, not built | 1.7 |
| Unit 15, Borrowmeadow Road | battery storage | 19 | abandoned | 2.3 |
| Easter Cringate Cottage, Polmaise Road | wind farm | 30 | application submitted | 2.6 |
| Farm at Lower Polmaise | solar farm | 5 | permission expired | 3.4 |
| Manor Powis | solar farm | 5 | application withdrawn | 4.4 |
| Glenside Farm | battery storage | 400 | approved, not built | 5.5 |
| Rullie Community Windfarm | wind farm | 25 | application withdrawn | 6.6 |
| Muirpark | wind farm | 33 | refused | 7.6 |
| Tod Hill Farm Wind Turbines | wind farm | 12 | operational | 7.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.097, -3.917).