Earlsburn Wind Farm Extension (34 MW)

Earlsburn Wind Farm Extension is a 34 MW wind farm project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 December 2025, not yet built; the record was last updated on 8 January 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

34 MWwind farm
approved, not builtstatus in REPD
8 January 2026record last updated
Stirlingcouncil area

Planning timeline

DateStage
23 December 2022Application submitted
16 December 2025Section 36 consent granted (Scottish Ministers)
16 December 2030Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
34 MW
Status (REPD)
approved, not built
Record last updated
8 January 2026
Operator or applicant
Naturalis Energy / REG Wind Power / Falck Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004510
Turbines
7
Turbine height
150 m
Address (REPD)
Earlsburn Avenue, Stirling
Council area (by location)
Stirling
Time to decision
156 weeks
Name in REPD
Earlsburn Avenue - Earlsburn Wind Farm Extension
REPD reference
11481

The scheme also includes 18 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Shelloch Wind Farmwind farm24approved, not built1.7
Easter Cringate Cottage, Polmaise Roadwind farm30application submitted2.3
Unit 15, Borrowmeadow Roadbattery storage19abandoned2.8
Farm at Lower Polmaisesolar farm5permission expired4.7
Manor Powissolar farm5application withdrawn5.2
Rullie Community Windfarmwind farm25application withdrawn6.2
Muirparkwind farm33refused6.2
Glenside Farmbattery storage400approved, not built6.5
Craigengeltwind farm20operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0984, -3.9445).