Rullie Community Windfarm (25 MW)
Rullie Community Windfarm is a 25 MW wind farm project in Falkirk, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 28 September 2012; the record was last updated on 19 October 2012.
25 MWwind farm
application withdrawnstatus in REPD
19 October 2012record last updated
Falkirkcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 16 December 2011 | Application submitted |
| 28 September 2012 | Application withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 25 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 19 October 2012
- Operator or applicant
- Community Windpower
- Planning authority
- Falkirk
- Planning application reference
- P/11/0800/FUL
- Turbines
- 10
- Address (REPD)
- N/West Of Burnhouse Farm, Denny, Central, FK6 6QY
- Council area (by location)
- Falkirk
- REPD reference
- 3763
Who decides
| Applications | Falkirk | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 3 (16%) | 19% |
| Solar refused | 0 of 8 | 12% |
| Onshore wind refused | 3 of 5 | 45% |
| Battery storage refused | 0 of 6 | 16% |
| Median time from submission to decision | 8.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Muirpark | wind farm | 33 | refused | 4.8 |
| Glenside Farm | battery storage | 400 | approved, not built | 5.1 |
| Craigengelt | wind farm | 20 | operational | 5.6 |
| Earlsburn Wind Farm Extension | wind farm | 34 | approved, not built | 6.2 |
| Tod Hill Farm Wind Turbines | wind farm | 12 | operational | 6.3 |
| Craigannet Wind Farm | wind farm | 15 | refused on appeal | 6.4 |
| Glenhead Farm (Upper) | solar farm | 5 | permission expired | 6.5 |
| Shelloch Wind Farm | wind farm | 24 | approved, not built | 6.6 |
| Land adjacent Bonnybridge Substation | battery storage | 19.9 | abandoned | 7.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0431, -3.9613).