Energy Projects Near You

Rullie Community Windfarm (25 MW)

Rullie Community Windfarm is a 25 MW wind farm project in Falkirk, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 28 September 2012; the record was last updated on 19 October 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWwind farm
application withdrawnstatus in REPD
19 October 2012record last updated
Falkirkcouncil area

Planning timeline

DateStage
16 December 2011Application submitted
28 September 2012Application withdrawn

Project details

Technology
wind farm
Capacity
25 MW
Status (REPD)
application withdrawn
Record last updated
19 October 2012
Operator or applicant
Community Windpower
Planning authority
Falkirk
Planning application reference
P/11/0800/FUL
Turbines
10
Address (REPD)
N/West Of Burnhouse Farm, Denny, Central, FK6 6QY
Council area (by location)
Falkirk
REPD reference
3763

Who decides

ApplicationsFalkirkUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused0 of 812%
Onshore wind refused3 of 545%
Battery storage refused0 of 616%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Muirparkwind farm33refused4.8
Glenside Farmbattery storage400approved, not built5.1
Craigengeltwind farm20operational5.6
Earlsburn Wind Farm Extensionwind farm34approved, not built6.2
Tod Hill Farm Wind Turbineswind farm12operational6.3
Craigannet Wind Farmwind farm15refused on appeal6.4
Glenhead Farm (Upper)solar farm5permission expired6.5
Shelloch Wind Farmwind farm24approved, not built6.6
Land adjacent Bonnybridge Substationbattery storage19.9abandoned7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0431, -3.9613).