Tod Hill Farm Wind Turbines (12 MW)
Tod Hill Farm Wind Turbines is a 12 MW wind farm project in Falkirk, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 January 2015; the record was last updated on 7 May 2015.
12 MWwind farm
operationalstatus in REPD
7 May 2015record last updated
Falkirkcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 17 June 2011 | Application submitted |
| 19 December 2011 | Appeal lodged |
| 21 December 2011 | Refused by the planning authority |
| 6 June 2012 | Planning permission granted |
| 6 June 2012 | Appeal allowed |
| 1 April 2014 | Construction started |
| 22 January 2015 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 12 MW
- Status (REPD)
- operational
- Record last updated
- 7 May 2015
- Operator or applicant
- Falkirk Tod Hill Wind Limited
- Planning authority
- Falkirk
- Planning application reference
- P/11/0326/FUL
- Appeal reference
- PPA-240-2022
- Turbines
- 4
- Address (REPD)
- Todhill Farm Larbert
- Council area (by location)
- Falkirk
- Time to decision
- 51 weeks
- REPD reference
- 3415
Who decides
| Applications | Falkirk | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 3 (16%) | 19% |
| Solar refused | 0 of 8 | 12% |
| Onshore wind refused | 3 of 5 | 45% |
| Battery storage refused | 0 of 6 | 16% |
| Median time from submission to decision | 8.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Glenside Farm | battery storage | 400 | approved, not built | 2.4 |
| Land adjacent Bonnybridge Substation | battery storage | 19.9 | abandoned | 2.6 |
| Merchiston Industrial Estate, Smith Street | battery storage | 43 | under construction | 5.4 |
| Rullie Community Windfarm | wind farm | 25 | application withdrawn | 6.3 |
| Shelloch Wind Farm | wind farm | 24 | approved, not built | 7.9 |
| Earlsburn Wind Farm Extension | wind farm | 34 | approved, not built | 8.9 |
| Forthbank | wind farm | 5 | refused | 9.0 |
| Farm at Lower Polmaise | solar farm | 5 | permission expired | 9.4 |
| Kincardine Battery Storage | battery storage | 342 | approved, not built | 9.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0325, -3.8621).