Energy Projects Near You

Tod Hill Farm Wind Turbines (12 MW)

Tod Hill Farm Wind Turbines is a 12 MW wind farm project in Falkirk, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 January 2015; the record was last updated on 7 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
operationalstatus in REPD
7 May 2015record last updated
Falkirkcouncil area

Planning timeline

DateStage
17 June 2011Application submitted
19 December 2011Appeal lodged
21 December 2011Refused by the planning authority
6 June 2012Planning permission granted
6 June 2012Appeal allowed
1 April 2014Construction started
22 January 2015Operational

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
7 May 2015
Operator or applicant
Falkirk Tod Hill Wind Limited
Planning authority
Falkirk
Planning application reference
P/11/0326/FUL
Appeal reference
PPA-240-2022
Turbines
4
Address (REPD)
Todhill Farm Larbert
Council area (by location)
Falkirk
Time to decision
51 weeks
REPD reference
3415

Who decides

ApplicationsFalkirkUK
Decided applications (solar, wind, battery)1910,236
Refused3 (16%)19%
Solar refused0 of 812%
Onshore wind refused3 of 545%
Battery storage refused0 of 616%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Glenside Farmbattery storage400approved, not built2.4
Land adjacent Bonnybridge Substationbattery storage19.9abandoned2.6
Merchiston Industrial Estate, Smith Streetbattery storage43under construction5.4
Rullie Community Windfarmwind farm25application withdrawn6.3
Shelloch Wind Farmwind farm24approved, not built7.9
Earlsburn Wind Farm Extensionwind farm34approved, not built8.9
Forthbankwind farm5refused9.0
Farm at Lower Polmaisesolar farm5permission expired9.4
Kincardine Battery Storagebattery storage342approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0325, -3.8621).