Kincardine Battery Storage (342 MW)

Kincardine Battery Storage is a 342 MW battery storage project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 July 2025, not yet built; the record was last updated on 26 August 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

342 MWbattery storage
approved, not builtstatus in REPD
26 August 2025record last updated
Fifecouncil area

Planning timeline

DateStage
1 August 2024Application submitted
22 July 2025Section 36 consent granted (Scottish Ministers)
22 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
342 MW
Status (REPD)
approved, not built
Record last updated
26 August 2025
Operator or applicant
Gresham House Devco Pipeline Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004987
Address (REPD)
West of Kincardine substation
Council area (by location)
Fife
Time to decision
51 weeks
REPD reference
15527

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Kincardine Grid Services Complex Energy Storage Facilitybattery storage400approved, not built1.0
Forthbankwind farm5refused3.3
West Grange Solar Farmsolar farm5abandoned6.3
Devilla Energy Storage Facilitybattery storage500under construction6.5
Balhearty Solarsolar farm5operational7.2
Bankhead Farmbattery storage25approved, not built7.4
Merchiston Industrial Estate, Smith Streetbattery storage43under construction7.9
Easter Muirhead Farmwind farm15refused8.4
Windburn Wind Farmwind farm65application submitted8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0796, -3.735).