Energy Projects Near You

West Grange Solar Farm (5 MW)

West Grange Solar Farm is a 5 MW solar farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 27 November 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
27 November 2019record last updated
Fifecouncil area

Planning timeline

DateStage
19 August 2016Application submitted
19 December 2016Planning permission granted
19 December 2019Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
27 November 2019
Operator or applicant
West Strathore Solar
Planning authority
Fife
Planning application reference
16/02840/FULL
Site area
13.9 ha
Address (REPD)
Land To The North Of, West Grange, West Grange Farm, Brankstone , Blairhall, Dunfermline,
Council area (by location)
Fife
Time to decision
17 weeks
REPD reference
6216

Earlier applications for this site

ApplicationMWSubmittedOutcome
West Grange Solar Farm 15/02928/FULL520 August 2015withdrawn 15 August 2016

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Muirmealing Solar Farmsolar farm5abandoned3.2
Easter Muirhead Farmwind farm15refused4.2
Kincardine Grid Services Complex Energy Storage Facilitybattery storage400approved, not built5.8
Kincardine Battery Storagebattery storage342approved, not built6.3
Balhearty Solarsolar farm5operational7.5
Craigluscar, Craigluscar Road Solar Array & Battery Storagesolar farm40approved, not built8.2
Forthbankwind farm5refused8.8
Nettly Burn Renewable Energy Parksolar farm80approved, not built9.1
Outh Muir Wind Farmwind farm12.5refused on appeal9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0905, -3.6354).