Craigluscar, Craigluscar Road Solar Array & Battery Storage (40 MW)

Craigluscar, Craigluscar Road Solar Array & Battery Storage is a 40 MW solar farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 July 2025, not yet built; the record was last updated on 25 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
25 July 2025record last updated
Fifecouncil area

Planning timeline

DateStage
30 September 2024Application submitted
3 July 2025Planning permission granted
3 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
25 July 2025
Operator or applicant
Locogen Consulting Limited
Planning authority
Fife
Planning application reference
24/02548/FULL
Site area
89.5 ha
Address (REPD)
Craigluscar Craigluscar Road Milesmark
Council area (by location)
Fife
Time to decision
39 weeks
Name in REPD
Craigluscar, Craigluscar Road - Solar Array & Battery Storage
REPD reference
13321

The scheme also includes 9.9 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dunfermline North Solar Photovoltaic Array/Battery storagesolar farm29.9under construction2.4
Nettly Burn Renewable Energy Parksolar farm80approved, not built3.8
Outh Muir Wind Farmwind farm12.5refused on appeal4.5
Blairadam Wind Farmwind farm22.6refused4.9
Kingdom of Fife Community Wind Parkwind farm12refused6.7
Muirmealing Solar Farmsolar farm5abandoned7.1
West Grange Solar Farmsolar farm5abandoned8.2
Babcock Marine Bldg, Wood Roadsolar farm5.6approved, not built8.5
Easter Muirhead Farmwind farm15refused8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.097, -3.5035).