Dunfermline North Solar Photovoltaic Array/Battery storage (29.9 MW)

Dunfermline North Solar Photovoltaic Array/Battery storage is a 29.9 MW solar farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 July 2024; the record was last updated on 12 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.9 MWsolar farm
under constructionstatus in REPD
12 May 2025record last updated
Fifecouncil area

Planning timeline

DateStage
26 April 2022Application submitted
23 June 2023Planning permission granted
1 July 2024Construction started

Project details

Technology
solar farm
Capacity
29.9 MW
Status (REPD)
under construction
Record last updated
12 May 2025
Operator or applicant
Dunfermline Solar Limited (AMPYR Solar Europe)
Planning authority
Fife
Planning application reference
22/01225/FULL
Site area
46.1 ha
Address (REPD)
S/O Lochead Landfill Site
Council area (by location)
Fife
Time to decision
60 weeks
Name in REPD
Dunfermline North - Solar Photovoltaic Array/Battery storage
REPD reference
11263

The scheme also includes 20 MW of battery storage, recorded separately in REPD (under construction).

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Craigluscar, Craigluscar Road Solar Array & Battery Storagesolar farm40approved, not built2.4
Blairadam Wind Farmwind farm22.6refused3.9
Kingdom of Fife Community Wind Parkwind farm12refused4.3
Nettly Burn Renewable Energy Parksolar farm80approved, not built4.5
Outh Muir Wind Farmwind farm12.5refused on appeal4.7
Cuttlehill Farm, Crossgatesbattery storage25abandoned6.7
South Pargillisbattery storage42approved, not built7.6
STOR Field 9battery storage37approved, not built8.0
Babcock Marine Bldg, Wood Roadsolar farm5.6approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0996, -3.4646).