Babcock Marine Bldg, Wood Road (5.6 MW solar farm)

Babcock Marine Bldg, Wood Road is a 5.6 MW solar farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 December 2023, not yet built; the record was last updated on 15 December 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.6 MWsolar farm
approved, not builtstatus in REPD
15 December 2023record last updated
Fifecouncil area

Planning timeline

DateStage
24 August 2023Application submitted
8 December 2023Planning permission granted
8 December 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
5.6 MW
Status (REPD)
approved, not built
Record last updated
15 December 2023
Operator or applicant
Babcock Marine
Planning authority
Fife
Planning application reference
23/02089/FULL
Site area
10.6 ha
Address (REPD)
Babcock Marine Bldg,180 Wood Road, Rosyth Business Park, Rosyth, Dunfermline
Council area (by location)
Fife
Time to decision
15 weeks
Name in REPD
Babcock Marine Bldg, Wood Road - Solar Photovoltaic Array
REPD reference
13382

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
STOR Field 9battery storage37approved, not built3.1
South Pargillisbattery storage42approved, not built4.4
Duddingston Solar Farm and Battery Storagesolar farm29.9approved, not built4.7
Kingdom of Fife Community Wind Parkwind farm12refused7.3
Parkend Crossgates Solar Panels & Battery Storagesolar farm30approved, not built7.9
Dunfermline North Solar Photovoltaic Array/Battery storagesolar farm29.9under construction8.0
Trinlaymire Farm Solar farm, Battery storagesolar farm29.9approved, not built8.1
Cuttlehill Farm, Crossgatesbattery storage25abandoned8.5
Craigluscar, Craigluscar Road Solar Array & Battery Storagesolar farm40approved, not built8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0285, -3.441).