Energy Projects Near You

Duddingston Solar Farm and Battery Storage (29.9 MW)

Duddingston Solar Farm and Battery Storage is a 29.9 MW solar farm project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 April 2024, not yet built; the record was last updated on 8 April 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.9 MWsolar farm
approved, not builtstatus in REPD
8 April 2024record last updated
West Lothiancouncil area

Planning timeline

DateStage
11 January 2024Application submitted
3 April 2024Planning permission granted
3 April 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
29.9 MW
Status (REPD)
approved, not built
Record last updated
8 April 2024
Operator or applicant
Aithrie Net Zero Solar Limited
Planning authority
West Lothian
Planning application reference
1016/FUL/23
Site area
45.5 ha
Address (REPD)
Duddingston, Newton, South Queensferry
Council area (by location)
West Lothian
Time to decision
12 weeks
Contracts for Difference
AR6
REPD reference
11382

The scheme also includes 20 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsWest LothianUK
Decided applications (solar, wind, battery)4110,236
Refused5 (12%)19%
Solar refused1 of 1712%
Onshore wind refused4 of 1545%
Battery storage refused0 of 916%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Trinlaymire Farm Solar farm, Battery storagesolar farm29.9approved, not built4.5
Babcock Marine Bldg, Wood Roadsolar farm5.6approved, not built4.7
Main Terminal 1 Edinburgh Airport Solar Farmsolar farm9approved, not built6.5
STOR Field 9battery storage37approved, not built6.6
Learielaw Farm, Learielawbattery storage100approved, not built6.8
Broxburnbattery storage20operational7.4
South Pargillisbattery storage42approved, not built8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9858, -3.4432).