Learielaw Farm, Learielaw (100 MW battery storage)

Learielaw Farm, Learielaw is a 100 MW battery storage project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 May 2025, not yet built; the record was last updated on 11 June 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
11 June 2025record last updated
West Lothiancouncil area

Planning timeline

DateStage
20 November 2023Application submitted
19 May 2025Section 36 consent granted (Scottish Ministers)
19 May 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
11 June 2025
Operator or applicant
Intelligent Land Investments Group
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004983
Address (REPD)
Learielaw Farm, Learielaw, Broxburn
Council area (by location)
West Lothian
Time to decision
78 weeks
Name in REPD
Learielaw Farm, Learielaw - Battery Energy Storage
REPD reference
13368

Earlier applications for this site

ApplicationMWSubmittedOutcome
Learielaw Farm 0600/FUL/2029.95 August 2020replaced by a revised application

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Broxburnbattery storage20operational0.7
Drumshoreland Road Battery Storage Facilitybattery storage49.9approved, not built3.9
Selms Muir Solar Farmsolar farm18approved, not built4.9
Trinlaymire Farm Solar farm, Battery storagesolar farm29.9approved, not built5.3
Drumcross Battery Storagebattery storage30approved, not built5.5
Leyden Roadsolar farm40application submitted5.9
Main Terminal 1 Edinburgh Airport Solar Farmsolar farm9approved, not built6.4
Duddingston Solar Farm and Battery Storagesolar farm29.9approved, not built6.8
Riccarton Mains Roadbattery storage150application submitted9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9256, -3.4584).