Energy Projects Near You

Trinlaymire Farm Solar farm, Battery storage (29.9 MW)

Trinlaymire Farm Solar farm, Battery storage is a 29.9 MW solar farm project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 December 2024, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.9 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
West Lothiancouncil area

Planning timeline

DateStage
23 August 2024Application submitted
20 December 2024Planning permission granted
20 December 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
29.9 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Trinlaymire Net Zero Solar Limited
Planning authority
West Lothian
Planning application reference
0568/FUL/24
Site area
60.8 ha
Address (REPD)
Trinlaymire Farm Threemiletown Linlithgow
Council area (by location)
West Lothian
Time to decision
17 weeks
Contracts for Difference
AR7a
Name in REPD
Trinlaymire Farm - Solar farm, Battery storage
REPD reference
11425

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsWest LothianUK
Decided applications (solar, wind, battery)4110,236
Refused5 (12%)19%
Solar refused1 of 1712%
Onshore wind refused4 of 1545%
Battery storage refused0 of 916%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Duddingston Solar Farm and Battery Storagesolar farm29.9approved, not built4.5
Learielaw Farm, Learielawbattery storage100approved, not built5.3
Broxburnbattery storage20operational6.0
Babcock Marine Bldg, Wood Roadsolar farm5.6approved, not built8.1
Drumshoreland Road Battery Storage Facilitybattery storage49.9approved, not built8.2
Drumcross Battery Storagebattery storage30approved, not built8.6
Main Terminal 1 Edinburgh Airport Solar Farmsolar farm9approved, not built9.0
Selms Muir Solar Farmsolar farm18approved, not built10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9651, -3.5053).