Energy Projects Near You

Broxburn (20 MW battery storage)

Broxburn is a 20 MW battery storage project in West Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 September 2018; the record was last updated on 18 April 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
operationalstatus in REPD
18 April 2019record last updated
West Lothiancouncil area

Planning timeline

DateStage
3 August 2016Application submitted
25 November 2016Planning permission granted
15 December 2016Appeal lodged
6 March 2017Appeal allowed
15 August 2017Construction started
15 September 2018Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
operational
Record last updated
18 April 2019
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
West Lothian
Planning application reference
LIVE/0502/FUL/16
Appeal reference
PPA-400-2073
Address (REPD)
Land at Lookabootye, by Broxburn, adjacent to the Lookabootye substation.
Council area (by location)
West Lothian
Time to decision
16 weeks
REPD reference
6910

Who decides

ApplicationsWest LothianUK
Decided applications (solar, wind, battery)4110,236
Refused5 (12%)19%
Solar refused1 of 1712%
Onshore wind refused4 of 1545%
Battery storage refused0 of 916%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Learielaw Farm, Learielawbattery storage100approved, not built0.7
Drumshoreland Road Battery Storage Facilitybattery storage49.9approved, not built3.4
Selms Muir Solar Farmsolar farm18approved, not built4.2
Drumcross Battery Storagebattery storage30approved, not built5.1
Leyden Roadsolar farm40application submitted5.2
Trinlaymire Farm Solar farm, Battery storagesolar farm29.9approved, not built6.0
Main Terminal 1 Edinburgh Airport Solar Farmsolar farm9approved, not built6.6
Duddingston Solar Farm and Battery Storagesolar farm29.9approved, not built7.4
Riccarton Mains Roadbattery storage150application submitted9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9192, -3.4554).