Energy Projects Near You

Main Terminal 1 Edinburgh Airport Solar Farm (9 MW)

Main Terminal 1 Edinburgh Airport Solar Farm is a 9 MW solar farm project in City of Edinburgh, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 October 2021, not yet built; the record was last updated on 17 March 2022. REPD also records that the planning permission expired on 25 October 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
17 March 2022record last updated
City of Edinburghcouncil area

REPD also records that the planning permission expired on 25 October 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
7 October 2021Application submitted
25 October 2021Planning permission granted
25 October 2024Permission expired

Project details

Technology
solar farm
Capacity
9 MW
Status (REPD)
approved, not built
Record last updated
17 March 2022
Operator or applicant
City of Edinburgh Council / Edinburgh Airport/ Ampyr Energy UK Development Limited
Planning authority
City of Edinburgh
Planning application reference
21/05261/PNE
Site area
6.5 ha
Address (REPD)
Main Terminal 1 Edinburgh Airport, Edinburgh
Council area (by location)
City of Edinburgh
Time to decision
3 weeks
Name in REPD
Main Terminal 1 Edinburgh Airport - Solar Farm
REPD reference
11672

Who decides

ApplicationsCity of EdinburghUK
Decided applications (solar, wind, battery)1610,236
Refused0 (0%)19%
Solar refused0 of 1612%
Median time from submission to decision8.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Riccarton Mains Roadbattery storage150application submitted6.3
Learielaw Farm, Learielawbattery storage100approved, not built6.4
Duddingston Solar Farm and Battery Storagesolar farm29.9approved, not built6.5
Broxburnbattery storage20operational6.6
Selms Muir Solar Farmsolar farm18approved, not built8.9
Trinlaymire Farm Solar farm, Battery storagesolar farm29.9approved, not built9.0
Drumshoreland Road Battery Storage Facilitybattery storage49.9approved, not built9.6
Leyden Roadsolar farm40application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9484, -3.3632).