Energy Projects Near You

Solar, wind and battery projects near Queensferry (EH30)

26 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EH30 (City of Edinburgh): 2 are waiting for a planning decision, 16 approved but not yet running, 6 operational. The largest live scheme is Learielaw Farm, Learielaw (100 MW battery storage, approved on 19 May 2025, not yet built), 7.6 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Forthwind (20 MW, approved, not built), 31.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26projects within 10 km
2awaiting a decision
16approved, not running
6operational

Projects within 10 km of EH30

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Duddingston Solar Farm and Battery Storagesolar farmsolar farm29.9approved, not builtupdated Apr 2024Jan 2024granted Apr 2024Apr 2024West Lothian2.9
Duddingston Solar Farm and Battery Storagebattery storagebattery storage20approved, not builtupdated Apr 2024Jan 2024granted Apr 2024Apr 2024West Lothian2.9
Newbridge - Ground mounted solar Pv panelssolar farmsolar farm1approved, not built may be out of dateupdated Apr 2022Mar 2022granted Aug 2022Apr 2022City of Edinburgh4.2
Main Terminal 1 Edinburgh Airport Solar Farmsolar farmsolar farm9approved, not built may be out of dateupdated Mar 2022Oct 2021granted Oct 2021Mar 2022City of Edinburgh4.6
Chariot Drive, Newbridge Roadrooftop solarrooftop solar1.2approved, not built may be out of dateupdated Nov 2022Sep 2022granted Nov 2022Nov 2022City of Edinburgh5.3
Babcock Marine Bldg, Wood Roadsolar farmsolar farm5.6approved, not builtupdated Dec 2023Aug 2023granted Dec 2023Dec 2023Fife5.5
STOR Field 9battery storagebattery storage37approved, not builtupdated Jun 2026Jun 2018granted Jun 2026Jun 2026Fife6.0
Trinlaymire Farm Solar farm, Battery storagesolar farmsolar farm29.9approved, not builtupdated Feb 2026Aug 2024granted Dec 2024Feb 2026West Lothian7.1
South Pargillisbattery storagebattery storage42approved, not built may be out of dateupdated Apr 2026Jan 2023granted Jun 2023Apr 2026Fife7.2
Learielaw Farm, Learielawbattery storagebattery storage100approved, not builtupdated Jun 2025Nov 2023granted May 2025Jun 2025West Lothian7.6
Broxburnbattery storagebattery storage20operationalupdated Apr 2019Aug 2016granted Nov 2016Apr 2019West Lothian8.2
F M C Land, Pitreavie Business Parkwind turbinewind turbine1.5operationalupdated Apr 2012Feb 2009granted Dec 2009Apr 2012Fife8.2
FMC Technologieswind farmwind farm1.5operationalupdated Dec 2011Feb 2009granted Dec 2009Dec 2011Fife8.5
Dunfermline EDI4rooftop solarrooftop solar1.9operationalupdated Feb 2020Aug 2018—Feb 2020Fife8.8
Brewster Brothers, Drumshoreland Roadsolar farmsolar farm1.7approved, not builtupdated Oct 2025Jun 2025granted Sep 2025Oct 2025West Lothian9.4
Smaller schemes under 1 MW, mostly rooftop solar (11)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
St Margarets Baysolar farmsolar farm0.2operationalupdated Mar 2020Feb 2019granted Apr 2019Mar 2020Fife3.9
Queen Anne Drive - Roof Mounted Solar PV Panelsrooftop solarrooftop solar0.6approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023City of Edinburgh5.4
Claylands Roadrooftop solarrooftop solar0.2operationalupdated May 2023Feb 2020granted Jul 2020May 2023City of Edinburgh6.1
Aldi Storesrooftop solarrooftop solar0.5application submittedupdated Mar 2025Feb 2025—Mar 2025Fife6.7
Trinlaymire Farm Solar farm, Battery storagebattery storagebattery storage—approved, not builtupdated Feb 2026Aug 2024granted Dec 2024Feb 2026West Lothian7.1
Energy Storage at Micro Energy Storage Project West Way Hillend Industrial Park Dalgety Baybattery storagebattery storage0.2approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025Fife7.2
Glasgow Road, Gogarrooftop solarrooftop solar0.5approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026City of Edinburgh7.8
Bankhead Crossway Southrooftop solarrooftop solar0.2application submittedApr 2026——City of Edinburgh9.1
Murrayfield Hospital, Corstorphine Roadrooftop solarrooftop solar0.6application withdrawnupdated Mar 2025Jul 2024—Mar 2025City of Edinburgh9.3
Uphall Business Park, Uphallrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Jan 2022Jan 2022granted Mar 2022Jan 2022West Lothian9.4
Uphall Park Developmentsolar farmsolar farm—refusedupdated Apr 2021Jan 2021refused Apr 2022Apr 2021West Lothian9.7

Distance from the average position of the EH30 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8061177.2
Rooftop solar924203.3
Wind farm100100
Wind turbine100100
Battery storage70610199

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Forthwind20approved, not builtupdated Aug 202331.2
Levenmouth demonstration turbine (Fife Energy Park)7operationalupdated Nov 201833.5

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How City of Edinburgh decides solar, wind and battery applications

ApplicationsCity of EdinburghUK
Decided applications (solar, wind, battery)1610,236
Refused0 (0%)19%
Solar refused0 of 1612%
Median time from submission to decision8.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in City of Edinburgh

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EH30, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.