STOR Field 9 (37 MW battery storage)

STOR Field 9 is a 37 MW battery storage project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 June 2026, not yet built; the record was last updated on 19 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

37 MWbattery storage
approved, not builtstatus in REPD
19 June 2026record last updated
Fifecouncil area

Planning timeline

DateStage
9 June 2018Application submitted
5 June 2026Planning permission granted
5 June 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
37 MW
Status (REPD)
approved, not built
Record last updated
19 June 2026
Operator or applicant
Capbal
Planning authority
Fife
Planning application reference
18/01583/PPP
Address (REPD)
Land East of North Road, Inverkeithing, Dunfermline, Fife
Council area (by location)
Fife
Time to decision
417 weeks
REPD reference
7018

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
South Pargillisbattery storage42approved, not built1.4
Babcock Marine Bldg, Wood Roadsolar farm5.6approved, not built3.1
Parkend Crossgates Solar Panels & Battery Storagesolar farm30approved, not built4.9
Kingdom of Fife Community Wind Parkwind farm12refused5.6
Cuttlehill Farm, Crossgatesbattery storage25abandoned6.1
Duddingston Solar Farm and Battery Storagesolar farm29.9approved, not built6.6
Mossmorran Wind Farmwind farm6application withdrawn7.5
Dunfermline North Solar Photovoltaic Array/Battery storagesolar farm29.9under construction8.0
Craigluscar, Craigluscar Road Solar Array & Battery Storagesolar farm40approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0389, -3.3948).