Energy Projects Near You

Parkend Crossgates Solar Panels & Battery Storage (30 MW)

Parkend Crossgates Solar Panels & Battery Storage is a 30 MW solar farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 March 2024, not yet built; the record was last updated on 8 April 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
8 April 2024record last updated
Fifecouncil area

Planning timeline

DateStage
28 November 2022Application submitted
7 March 2024Planning permission granted
7 March 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
8 April 2024
Operator or applicant
Greentech Projects Holding UK Limited
Planning authority
Fife
Planning application reference
22/03982/FULL
Site area
32.6 ha
Address (REPD)
Parkend Crossgates
Council area (by location)
Fife
Time to decision
66 weeks
Contracts for Difference
AR6
Name in REPD
Parkend Crossgates - Solar Panels & Battery Storage
REPD reference
11861

The scheme also includes 9 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cuttlehill Farm, Crossgatesbattery storage25abandoned2.3
Mossmorran Wind Farmwind farm6application withdrawn2.5
South Pargillisbattery storage42approved, not built3.5
Kingdom of Fife Community Wind Parkwind farm12refused4.0
STOR Field 9battery storage37approved, not built4.9
Mossmorran Battery Storagebattery storage300approved, not built6.0
Gleniston, Auchtertoolbattery storage49.5approved, not built6.1
Camilla Battery Storagebattery storage50operational6.2
Glenniston Farm, Auchtertool Solar Farmsolar farm39approved, not built6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0716, -3.3408).