Energy Projects Near You

Glenniston Farm, Auchtertool Solar Farm (39 MW)

Glenniston Farm, Auchtertool Solar Farm is a 39 MW solar farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 April 2024, not yet built; the record was last updated on 3 February 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

39 MWsolar farm
approved, not builtstatus in REPD
3 February 2025record last updated
Fifecouncil area

Planning timeline

DateStage
14 September 2023Application submitted
5 April 2024Planning permission granted
5 April 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
39 MW
Status (REPD)
approved, not built
Record last updated
3 February 2025
Operator or applicant
Locogen Consulting Limited
Planning authority
Fife
Planning application reference
23/02598/FULL
Site area
71.0 ha
Address (REPD)
Glenniston Farm Gleniston Auchtertool Lochgelly
Council area (by location)
Fife
Time to decision
29 weeks
Contracts for Difference
AR6
Name in REPD
Glenniston Farm, Auchtertool - Solar Farm
REPD reference
10433

The scheme also includes 10 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gleniston, Auchtertoolbattery storage49.5approved, not built0.3
Camilla Battery Storagebattery storage50operational0.5
Mossmorran Battery Storagebattery storage300approved, not built1.1
Clentrie Wind Farm (Gevens)wind farm6.9operational1.3
Little Raith Farmwind farm25operational1.4
Little Raith Farm - extensionwind farm18refused on appeal1.4
Mossmorran Wind Farmwind farm6application withdrawn3.8
Westfieldwind farm10operational3.9
Strathruddie, Kinglassie Solar farmsolar farm25approved, not built5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1129, -3.2713).