Clentrie Wind Farm (Gevens) (6.9 MW)
Clentrie Wind Farm (Gevens) is a 6.9 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 October 2016; the record was last updated on 4 July 2017.
6.9 MWwind farm
operationalstatus in REPD
4 July 2017record last updated
Fifecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 22 September 2011 | Application submitted |
| 15 May 2014 | Planning permission granted |
| 1 February 2016 | Construction started |
| 24 October 2016 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 6.9 MW
- Status (REPD)
- operational
- Record last updated
- 4 July 2017
- Operator or applicant
- Rev Ltd
- Planning authority
- Fife
- Planning application reference
- 11/04794/EIA
- Turbines
- 3
- Address (REPD)
- Clentrie Farm, Fife
- Council area (by location)
- Fife
- Time to decision
- 138 weeks
- REPD reference
- 4078
Who decides
| Applications | Fife | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 91 | 10,236 |
| Refused | 17 (19%) | 19% |
| Solar refused | 0 of 36 | 12% |
| Onshore wind refused | 16 of 30 | 45% |
| Battery storage refused | 1 of 25 | 16% |
| Median time from submission to decision | 24.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Little Raith Farm | wind farm | 25 | operational | 0.2 |
| Little Raith Farm - extension | wind farm | 18 | refused on appeal | 0.2 |
| Glenniston Farm, Auchtertool Solar Farm | solar farm | 39 | approved, not built | 1.3 |
| Camilla Battery Storage | battery storage | 50 | operational | 1.3 |
| Gleniston, Auchtertool | battery storage | 49.5 | approved, not built | 1.4 |
| Mossmorran Battery Storage | battery storage | 300 | approved, not built | 1.6 |
| Westfield | wind farm | 10 | operational | 4.0 |
| Mossmorran Wind Farm | wind farm | 6 | application withdrawn | 5.0 |
| Strathruddie, Kinglassie Solar farm | solar farm | 25 | approved, not built | 5.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1177, -3.2526).