Solar, wind and battery projects near Cowdenbeath (KY4)
41 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KY4 (Fife): 2 are waiting for a planning decision, 21 approved but not yet running, 9 operational. The largest live scheme is Mossmorran Battery Storage (300 MW battery storage, approved on 6 May 2025, not yet built), 6.3 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Forthwind (20 MW, approved, not built), 23.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of KY4
Projects of 1 MW and more (36)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Cuddyhouse Roadwind turbine | wind turbine | 1.5 | application withdrawnupdated Jul 2014 | Mar 2014 | — | Jul 2014 | Fife | 2.3 |
| Cuttlehill Farm, Crossgatesbattery storage | battery storage | 25 | abandonedupdated Oct 2021 | Apr 2018 | — | Oct 2021 | Fife | 2.7 |
| Kingdom of Fife Community Wind Parkwind farm | wind farm | 12 | refusedupdated Oct 2013 | Jul 2011 | refused Oct 2013 | Oct 2013 | Fife | 3.4 |
| Mossmorran Wind Farmwind farm | wind farm | 6 | application withdrawnupdated Feb 2014 | Jun 2012 | — | Feb 2014 | Fife | 3.8 |
| Mossmorran Wind Farmwind farm | wind farm | 4.6 | operationalupdated Apr 2016 | Apr 2011 | granted Jan 2012 | Apr 2016 | Fife | 3.8 |
| Goathill Quarry Turbinewind turbine | wind turbine | 2 | operationalupdated Apr 2016 | Nov 2011 | granted Jun 2013 | Apr 2016 | Fife | 4.1 |
| J2awind farm | wind farm | 4.7 | abandonedupdated Jun 2016 | Jan 2014 | — | Jun 2016 | Fife | 4.4 |
| Parkend Crossgates Solar Panels & Battery Storagesolar farm | solar farm | 30 | approved, not builtupdated Apr 2024 | Nov 2022 | granted Mar 2024 | Apr 2024 | Fife | 4.9 |
| Parkend Crossgates Solar Panels & Battery Storagebattery storage | battery storage | 9 | approved, not builtupdated Apr 2024 | Nov 2022 | granted Mar 2024 | Apr 2024 | Fife | 5.3 |
| Westfieldwind farm | wind farm | 10 | operationalupdated Jun 2013 | Jul 2009 | granted Jun 2012 | Jun 2013 | Fife | 5.5 |
| Glenniston Farm, Auchtertool Solar Farmsolar farm | solar farm | 39 | approved, not builtupdated Feb 2025 | Sep 2023 | granted Apr 2024 | Feb 2025 | Fife | 5.7 |
| Gleniston, Auchtertoolbattery storage | battery storage | 49.5 | approved, not built may be out of dateupdated Nov 2022 | Jul 2022 | granted Nov 2022 | Nov 2022 | Fife | 5.7 |
| Dunfermline EDI4rooftop solar | rooftop solar | 1.9 | operationalupdated Feb 2020 | Aug 2018 | — | Feb 2020 | Fife | 5.8 |
| Camilla Battery Storagebattery storage | battery storage | 50 | operationalupdated Mar 2024 | Aug 2020 | granted Oct 2022 | Mar 2024 | Fife | 6.0 |
| Glenniston Farm, Auchtertool Solar Farmbattery storage | battery storage | 10 | approved, not builtupdated Feb 2025 | Sep 2023 | granted Apr 2024 | Feb 2025 | Fife | 6.1 |
| Mossmorran Battery Storagebattery storage | battery storage | 300 | approved, not builtupdated Jul 2025 | Jun 2024 | granted May 2025 | Jul 2025 | Fife | 6.3 |
| Dunfermline North Solar Photovoltaic Array/Battery storagesolar farm | solar farm | 29.9 | under constructionupdated May 2025 | Apr 2022 | granted Jun 2023 | May 2025 | Fife | 6.5 |
| Dunfermline North Solar Photovoltaic Array/Battery storagebattery storage | battery storage | 20 | under constructionupdated May 2025 | Apr 2022 | granted Jun 2023 | May 2025 | Fife | 6.5 |
| Blairadam Wind Farmwind farm | wind farm | 22.6 | refusedupdated Nov 2016 | Jan 2014 | refused Oct 2016 | Nov 2016 | Fife | 6.7 |
| Former Fife Power Stationbattery storage | battery storage | 100 | application submittedupdated Oct 2025 | Feb 2025 | — | Oct 2025 | Fife | 6.8 |
| Clentrie Wind Farm (Gevens)wind farm | wind farm | 6.9 | operationalupdated Jul 2017 | Sep 2011 | granted May 2014 | Jul 2017 | Fife | 6.8 |
| Little Raith Farmwind farm | wind farm | 25 | operationalupdated Sep 2020 | Dec 2004 | granted Mar 2007 | Sep 2020 | Fife | 6.9 |
| Little Raith Farm - extensionwind farm | wind farm | 18 | refused on appealupdated Jul 2015 | Jul 2014 | refused Jun 2015 | Jul 2015 | Fife | 6.9 |
| South Pargillisbattery storage | battery storage | 42 | approved, not built may be out of dateupdated Apr 2026 | Jan 2023 | granted Jun 2023 | Apr 2026 | Fife | 7.3 |
| FMC Technologieswind farm | wind farm | 1.5 | operationalupdated Dec 2011 | Feb 2009 | granted Dec 2009 | Dec 2011 | Fife | 8.2 |
| F M C Land, Pitreavie Business Parkwind turbine | wind turbine | 1.5 | operationalupdated Apr 2012 | Feb 2009 | granted Dec 2009 | Apr 2012 | Fife | 8.4 |
| Strathruddie, Kinglassie Solar farmsolar farm | solar farm | 25 | approved, not built may be out of dateupdated Oct 2024 | Nov 2021 | granted Mar 2022 | Oct 2024 | Fife | 8.5 |
| Strathruddie, Kinglassie Solar farmbattery storage | battery storage | 20 | approved, not built may be out of dateupdated Oct 2024 | Nov 2021 | granted Mar 2022 | Oct 2024 | Fife | 8.5 |
| Westfield Solar Farm & Batterysolar farm | solar farm | 30 | approved, not builtupdated Mar 2026 | Sep 2020 | granted Feb 2021 | Mar 2026 | Fife | 8.5 |
| Westfield Solar Farm & Batterybattery storage | battery storage | 20 | approved, not builtupdated Mar 2026 | Sep 2020 | granted Feb 2021 | Mar 2026 | Fife | 8.5 |
| STOR Field 9battery storage | battery storage | 37 | approved, not builtupdated Jun 2026 | Jun 2018 | granted Jun 2026 | Jun 2026 | Fife | 8.6 |
| Craigluscar, Craigluscar Road Solar Array & Battery Storagebattery storage | battery storage | 9.9 | approved, not builtupdated Jul 2025 | Sep 2024 | granted Jul 2025 | Jul 2025 | Fife | 8.7 |
| Outh Muir Wind Farmwind farm | wind farm | 12.5 | refused on appealupdated Sep 2014 | Jul 2013 | refused Mar 2014 | Sep 2014 | Fife | 8.8 |
| Craigluscar, Craigluscar Road Solar Array & Battery Storagesolar farm | solar farm | 40 | approved, not builtupdated Jul 2025 | Sep 2024 | granted Jul 2025 | Jul 2025 | Fife | 8.9 |
| Nettly Burn Renewable Energy Parksolar farm | solar farm | 80 | approved, not builtupdated Jun 2026 | Oct 2024 | granted Mar 2026 | Jun 2026 | Fife | 9.3 |
| Nettly Burn Renewable Energy Parkbattery storage | battery storage | 15 | approved, not builtupdated Jun 2026 | Oct 2024 | granted Mar 2026 | Jun 2026 | Fife | 9.3 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Water Treatment Works,Seco Placerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jun 2024 | Feb 2024 | granted Jun 2024 | Jun 2024 | Fife | 1.9 |
| Energy Storage Batterybattery storage | battery storage | 0.2 | approved, not builtupdated Aug 2025 | May 2025 | granted Aug 2025 | Aug 2025 | Fife | 4.1 |
| Westfield Restoration and Regeneration Projectbattery storage | battery storage | — | abandonedupdated Apr 2019 | Oct 2016 | — | Apr 2019 | Fife | 7.4 |
| Energy Storage at Micro Energy Storage Project West Way Hillend Industrial Park Dalgety Baybattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2025 | May 2025 | granted Jun 2025 | Jul 2025 | Fife | 7.8 |
| Aldi Storesrooftop solar | rooftop solar | 0.5 | application submittedupdated Mar 2025 | Feb 2025 | — | Mar 2025 | Fife | 8.0 |
Distance from the average position of the KY4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 7 | 0 | 0 | 274 |
| Rooftop solar | 3 | 1 | 1 | 1 | 0 | 1.1 |
| Wind farm | 11 | 0 | 0 | 5 | 4 | 0 |
| Wind turbine | 3 | 0 | 0 | 2 | 0 | 0 |
| Battery storage | 17 | 1 | 13 | 1 | 0 | 633 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Forthwind | 20 | approved, not builtupdated Aug 2023 | 23.1 |
| Levenmouth demonstration turbine (Fife Energy Park) | 7 | operationalupdated Nov 2018 | 25.6 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Fife decides solar, wind and battery applications
| Applications | Fife | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 91 | 10,236 |
| Refused | 17 (19%) | 19% |
| Solar refused | 0 of 36 | 12% |
| Onshore wind refused | 16 of 30 | 45% |
| Battery storage refused | 1 of 25 | 16% |
| Median time from submission to decision | 24.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KY4, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.