Former Fife Power Station (100 MW battery storage)

Former Fife Power Station is a 100 MW battery storage project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 6 February 2025, no decision recorded; the record was last updated on 14 October 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
application submittedstatus in REPD
14 October 2025record last updated
Fifecouncil area

Planning timeline

DateStage
6 February 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
application submitted
Record last updated
14 October 2025
Operator or applicant
Fife Power 1 Ltd
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005188
Address (REPD)
Woodend, Cardenden
Council area (by location)
Fife
Name in REPD
Former Fife Power Station - Battery Energy Storage System
REPD reference
17018

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Westfield Solar Farm & Batterysolar farm30approved, not built1.7
Westfieldwind farm10operational2.1
Strathruddie, Kinglassie Solar farmsolar farm25approved, not built2.6
Little Raith Farmwind farm25operational5.8
Little Raith Farm - extensionwind farm18refused on appeal5.8
Clentrie Wind Farm (Gevens)wind farm6.9operational6.0
Glenniston Farm, Auchtertool Solar Farmsolar farm39approved, not built6.0
Gleniston, Auchtertoolbattery storage49.5approved, not built6.3
Camilla Battery Storagebattery storage50operational6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1644, -3.3).