Energy Projects Near You

Solar, wind and battery projects near Kinross (KY13)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KY13 (Perth and Kinross): 1 is waiting for a planning decision, 5 approved but not yet running. The largest live scheme is Former Fife Power Station (100 MW battery storage, application submitted on 6 February 2025, no decision recorded), 9.7 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Forthwind (20 MW, approved, not built), 27.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
1awaiting a decision
5approved, not running
0operational

Projects within 10 km of KY13

Projects of 1 MW and more (13)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Balado Windfarmwind farmwind farm5.6refusedupdated Sep 2004Aug 2002refused Jan 2004Sep 2004Perth and Kinross1.6
Tillyriewind farmwind farm4.2refusedupdated Dec 2005Mar 2005refused Dec 2005Dec 2005Perth and Kinross5.8
Milnathort Community Wind Clusterwind farmwind farm2.4refused on appealupdated Jan 2014Oct 2012refused Aug 2013Jan 2014Perth and Kinross6.0
Shire-End Farmsolar farmsolar farm17approved, not built may be out of dateupdated Feb 2025Dec 2014granted Feb 2016Feb 2025Perth and Kinross7.0
Blairadam Wind Farmwind farmwind farm22.6refusedupdated Nov 2016Jan 2014refused Oct 2016Nov 2016Fife8.4
Outh Muir Wind Farmwind farmwind farm12.5refused on appealupdated Sep 2014Jul 2013refused Mar 2014Sep 2014Fife8.9
Mellock Hill Wind Farmwind farmwind farm48refusedupdated Jan 2010Oct 2004refused Jun 2005Jan 2010Perth and Kinross9.4
Mellock Hill Wind Farm IIwind farmwind farm35application withdrawnupdated May 2006Aug 2005—May 2006Perth and Kinross9.4
Westfield Solar Farm & Batterysolar farmsolar farm30approved, not builtupdated Mar 2026Sep 2020granted Feb 2021Mar 2026Fife9.7
Westfield Solar Farm & Batterybattery storagebattery storage20approved, not builtupdated Mar 2026Sep 2020granted Feb 2021Mar 2026Fife9.7
Former Fife Power Stationbattery storagebattery storage100application submittedupdated Oct 2025Feb 2025—Oct 2025Fife9.7
Nettly Burn Renewable Energy Parksolar farmsolar farm80approved, not builtupdated Jun 2026Oct 2024granted Mar 2026Jun 2026Fife9.7
Nettly Burn Renewable Energy Parkbattery storagebattery storage15approved, not builtupdated Jun 2026Oct 2024granted Mar 2026Jun 2026Fife9.7

Distance from the average position of the KY13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm30300127
Wind farm700060
Battery storage31200135

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Forthwind20approved, not builtupdated Aug 202327.7
Levenmouth demonstration turbine (Fife Energy Park)7operationalupdated Nov 201830.0

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Perth and Kinross decides solar, wind and battery applications

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

All projects in Perth and Kinross

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KY13, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.