Energy Projects Near You

Balado Windfarm (5.6 MW)

Balado Windfarm is a 5.6 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 1 January 2004; the record was last updated on 9 September 2004.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.6 MWwind farm
refusedstatus in REPD
9 September 2004record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
30 August 2002Application submitted
1 January 2004Refused by the planning authority

Project details

Technology
wind farm
Capacity
5.6 MW
Status (REPD)
refused
Record last updated
9 September 2004
Operator or applicant
Glen Devon Energy Ltd
Planning authority
Perth and Kinross
Planning application reference
02-01464-FUL
Appeal reference
P/PPA/340/283
Address (REPD)
Balado Kinross
Council area (by location)
Perth and Kinross
Time to decision
70 weeks
REPD reference
3187

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Shire-End Farmsolar farm17approved, not built7.0
Blairadam Wind Farmwind farm22.6refused8.0
Mellock Hill Wind Farmwind farm48refused8.0
Mellock Hill Wind Farm IIwind farm35application withdrawn8.0
Outh Muir Wind Farmwind farm12.5refused on appeal8.0
Nettly Burn Renewable Energy Parksolar farm80approved, not built8.9
Earnieside Farmhouse, Dunning Glen Wind Farmwind farm48approved, not built8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2065, -3.4605).