Energy Projects Near You

Renewable energy projects in Perth and Kinross

106 solar, wind or battery projects of 150 kW or more are located in Perth and Kinross (REPD, July 2026 extract): 11 pending, 35 approved but not running, 20 operational and 26 refused. The council refused 32 of 73 decided applications (44%; UK 19%), with a median 28 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

106projects in the council area
11awaiting a decision
35approved, not running
44%of decisions refused

How Perth and Kinross decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Projects in Perth and Kinross

Projects of 1 MW and more (93)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Haughend Farm - Alyth Battery Energy Storage Systembattery storagebattery storage900approved, not builtupdated Dec 2024Dec 2022granted Nov 2024Dec 2024
Griffin Wind farmwind farmwind farm156operationalupdated Feb 2012Apr 2004granted Jan 2008Feb 2012
Wind Farm at Meall Dearg Wind Farmwind farmwind farm147application submittedupdated Oct 2025Aug 2025—Oct 2025
Brunt Hill Wind Farm & Battery Storagewind farmwind farm130application submitted may be out of dateupdated Jun 2024May 2024—Jun 2024
Hallyburtonbattery storagebattery storage100approved, not builtupdated Dec 2025Dec 2024granted Oct 2025Dec 2025
Solar Array at Dupplin Solar 750 Metres S/O Newbigging Farm Tibbermoresolar farmsolar farm97.5application submittedupdated Jun 2026Mar 2026—Jun 2026
Crossburns Wind Farmwind farmwind farm75refused on appealupdated Oct 2017Oct 2014refused Oct 2017Oct 2017
Abercairneywind farmwind farm66refused on appealupdated Jan 2010Jan 2004refused Oct 2006Jan 2010
Knoweheadwind farmwind farm60refusedupdated Dec 2010Aug 2004refused Jul 2005Dec 2010
Stirling Battery and Solar Energy Parksolar farmsolar farm60approved, not builtupdated May 2026May 2024granted Feb 2026May 2026
Dulater Hill Wind Farmwind farmwind farm57.8refused on appealupdated Jun 2019Jun 2014refused May 2019Jun 2019
Lochelbank Wind Farmwind farmwind farm51application withdrawnupdated Apr 2009——Apr 2009
Brunt Hill Wind Farm & Battery Storagebattery storagebattery storage50application submitted may be out of dateupdated Jun 2024May 2024—Jun 2024
Stirling Battery and Solar Energy Parkbattery storagebattery storage50approved, not builtupdated May 2026May 2024granted Feb 2026May 2026
Shindour, Feddal Hill Woodbattery storagebattery storage50approved, not builtupdated Jan 2025Jan 2023granted Oct 2024Jan 2025
Old Gallows Roadbattery storagebattery storage49.9approved, not built may be out of dateupdated Feb 2024Apr 2021granted Aug 2021Feb 2024
Shindour Energy Storage Facilitybattery storagebattery storage49.9approved, not built may be out of dateupdated Feb 2025May 2021granted Dec 2021Feb 2025
Newhouse Farm Energy Storage Facilitybattery storagebattery storage49.9approved, not built may be out of dateupdated Jul 2022Jul 2022granted Jan 2023Jul 2022
Pleasance Road Battery Energy Facilitybattery storagebattery storage49.9operationalupdated Mar 2024Feb 2022granted Jun 2022Mar 2024
Newburgh Road, Abernethybattery storagebattery storage49.9approved, not built may be out of dateupdated May 2025May 2022granted Sep 2022May 2025
Milton Of Collace, Burrelton Solar Farmsolar farmsolar farm49.9refusedupdated Jul 2025Mar 2024refused Jun 2025Jul 2025
Dormitories Star Inn Farm, Mains Of Fowlisbattery storagebattery storage49.9approved, not builtupdated Jan 2024Aug 2023granted Dec 2023Jan 2024
Kinnon Park Farm, Methven Solar Farm & Battery Storagesolar farmsolar farm49.9refusedupdated Jun 2026Sep 2024refused May 2026Jun 2026
Coupar Angus Substation, Pleasance Road Solar Farmsolar farmsolar farm49.9refusedupdated Jan 2024Aug 2023refused Dec 2023Jan 2024
Taigh An Struith, Tibbermorebattery storagebattery storage49.9refusedupdated Mar 2025Jun 2024refused Mar 2025Mar 2025
Milton Of Collace, Burrelton Solar Farmsolar farmsolar farm49.9refusedupdated Jul 2025Mar 2024refused Jun 2025Jul 2025
Coupar Angus, Pleasance Road Battery Energy Facilitybattery storagebattery storage49.9approved, not builtupdated Sep 2024Mar 2024granted Sep 2024Sep 2024
Newburgh Road, Abernethybattery storagebattery storage49.9approved, not builtupdated Jun 2025Nov 2024granted May 2025Jun 2025
Tir Artairbattery storagebattery storage49.9approved, not builtupdated Jun 2026Apr 2025granted May 2026Jun 2026
West Pitnacree Farm, Alythsolar farmsolar farm49.9application submittedupdated Jun 2025May 2025—Jun 2025
Jamesfield Garden Centre, Newburghbattery storagebattery storage49.9application submittedupdated Mar 2026Feb 2026—Mar 2026
Jamesfield Organic Centrebattery storagebattery storage49operationalupdated Mar 2024May 2022granted Sep 2022Mar 2024
Mellock Hill Wind Farmwind farmwind farm48refusedupdated Jan 2010Oct 2004refused Jun 2005Jan 2010
Earnieside Farmhouse, Dunning Glen Wind Farmwind farmwind farm48approved, not builtupdated Dec 2025Aug 2024granted Nov 2025Dec 2025
Binn Farm Solar Farmsolar farmsolar farm39application submittedupdated Feb 2026Jan 2026—Feb 2026
Drumdergwind farmwind farm36.8operationalupdated Oct 2013Nov 2003granted Feb 2005Oct 2013
Mellock Hill Wind Farm IIwind farmwind farm35application withdrawnupdated May 2006Aug 2005—May 2006
Green Burn Wind Farmwind farmwind farm33abandonedupdated Dec 2021Oct 2015granted Feb 2018Dec 2021
Calliacharwind farmwind farm32.2operationalupdated Dec 2013Feb 2004granted Sep 2007Dec 2013
Glen Tarkenwind farmwind farm30application withdrawnupdated Oct 2006——Oct 2006
Cordon Farm, Abernethybattery storagebattery storage30application submittedupdated Oct 2025Oct 2024—Oct 2025
Creag A Bhairdwind farmwind farm29.9refused on appealupdated Jul 2015Feb 2014refused Mar 2015Jul 2015
Logiealmondwind farmwind farm28application withdrawnupdated Apr 2008Sep 2007—Apr 2008
Green Knoweswind farmwind farm27operationalupdated May 2016Aug 2004granted Jun 2008May 2016
Little Law Wind Farmwind farmwind farm27refused on appealupdated Dec 2014Jun 2004refused Jun 2005Dec 2014
Burnfoot Hillwind farmwind farm26operationalupdated Nov 2010Mar 2006granted Mar 2007Nov 2010
Snowgoat Glen Wind Farmwind farmwind farm23.5application withdrawnupdated May 2006Jul 2004—May 2006
Mull Hill Windfarmwind farmwind farm22.5refused on appealupdated Jun 2014Dec 2011refused May 2013Jun 2014
Mill Of Peattie Farm, Kinnochtry Coupar Solar Farmsolar farmsolar farm22refusedupdated Jul 2025Feb 2025refused Jul 2025Jul 2025
North Calliachar Wind Farmwind farmwind farm21abandonedupdated Mar 2019Apr 2013granted Mar 2015Mar 2019
Strathallan Wind Farmwind farmwind farm20.7under constructionupdated Feb 2023Oct 2015granted Jan 2019Feb 2023
Mains Of Keithick Farm, Keithick Battery Storage & Solar Farmsolar farmsolar farm20.5approved, not builtupdated Feb 2026Jul 2022granted Mar 2025Feb 2026
Bandirran Wind Farmwind farmwind farm20.4application withdrawnupdated Jul 2015Jan 2014—Jul 2015
Standingfauld Farmwind farmwind farm20refused on appealupdated Jan 2012Dec 2009refused May 2011Jan 2012
Mill Of Peattie Farm, Kinnochtry Couparbattery storagebattery storage18refusedupdated Jul 2025Feb 2025refused Jul 2025Jul 2025
Shire-End Farmsolar farmsolar farm17approved, not built may be out of dateupdated Feb 2025Dec 2014granted Feb 2016Feb 2025
Mains Of Keithick Farm, Keithick Battery Storage & Solar Farmbattery storagebattery storage16approved, not builtupdated Feb 2026Jul 2022granted Mar 2023Feb 2026
Newburgh Road, Abernethybattery storagebattery storage15approved, not built may be out of dateupdated Jul 2025Jan 2022granted Mar 2023Jul 2025
Tullymurdoch Wind Farmwind farmwind farm14.4operationalupdated Apr 2018Aug 2012granted Sep 2014Apr 2018
Frandy Hillwind farmwind farm14refused on appealupdated Nov 2013Dec 2011refused Apr 2013Nov 2013
Standingfauld Farm, Muthillsolar farmsolar farm14approved, not built may be out of dateupdated Feb 2023Aug 2022granted Nov 2022Feb 2023
Errol Estatesolar farmsolar farm13operationalupdated Jun 2016Mar 2014granted Jun 2014Jun 2016
Snowgoat Glen Wind Farm IIwind farmwind farm13refusedupdated May 2006Jun 2005refused Nov 2005May 2006
Rhodders Wind Farmwind farmwind farm12operationalupdated Feb 2016Nov 2011granted Jan 2014Feb 2016
Parks of Kellour Wind Farmwind farmwind farm12refusedupdated Aug 2015Mar 2015refused Jul 2015Aug 2015
Burnfoot East Wind Farm (further extension)wind farmwind farm10.8operationalupdated Feb 2024Jan 2017granted Mar 2019Feb 2024
Green knowes Windfarm Ext.wind farmwind farm10application withdrawnupdated Mar 2017Dec 2015—Mar 2017
Binn Eco Park Wind Farmwind farmwind farm10operationalupdated Jul 2018Nov 2014granted Aug 2015Jul 2018
Carey Solar Farmsolar farmsolar farm10permission expiredupdated Sep 2020Aug 2015granted Nov 2015Sep 2020
Cordon Farmsolar farmsolar farm10permission expiredupdated Sep 2020Mar 2017granted Jul 2017Sep 2020
Binn Eco Park Wind Farmwind farmwind farm10refusedupdated Dec 2019May 2018refused Apr 2019Dec 2019
Shindour Feddal Hill Wood Bracobattery storagebattery storage10abandonedupdated Jan 2023Oct 2017—Jan 2023
Binn Eco Park Batterybattery storagebattery storage10approved, not built may be out of dateupdated Jul 2024May 2021granted Jul 2021Jul 2024
Lochelbank Wind Farm IIwind farmwind farm9.6operationalupdated Jun 2011Apr 2005granted Aug 2007Jun 2011
Welton Of Creuchieswind farmwind farm9.2operationalupdated Apr 2018May 2010granted Jul 2012Apr 2018
Welton of Creuchieswind farmwind farm9.2application withdrawnupdated Oct 2015Sep 2015—Oct 2015
Knowes Farmwind farmwind farm7.7refusedupdated Jan 2015May 2014refused Dec 2014Jan 2015
Rowan Gate Solar Farmsolar farmsolar farm7approved, not built may be out of dateupdated Aug 2025Apr 2022granted Jul 2022Aug 2025
Binn Farm Solar Farmbattery storagebattery storage6application submittedupdated Feb 2026Jan 2026—Feb 2026
Balado Windfarmwind farmwind farm5.6refusedupdated Sep 2004Aug 2002refused Jan 2004Sep 2004
Jamesfield Solar Farmsolar farmsolar farm5permission expiredupdated Sep 2018Jun 2015granted Aug 2015Sep 2018
Binn Eco Park Solarsolar farmsolar farm5approved, not built may be out of dateupdated Feb 2024May 2021granted Sep 2021Feb 2024
Tillyriewind farmwind farm4.2refusedupdated Dec 2005Mar 2005refused Dec 2005Dec 2005
Burnfoot Hill Extensionwind farmwind farm4operationalupdated Sep 2014Dec 2011granted Apr 2013Sep 2014
Milnathort Community Wind Clusterwind farmwind farm2.4refused on appealupdated Jan 2014Oct 2012refused Aug 2013Jan 2014
Ardlebank Farm Wind Clusterwind farmwind farm2.4refusedupdated Jul 2013Sep 2011refused Jun 2013Jul 2013
Simon Howie Butchers, Findony Farmwind turbinewind turbine2.3approved, not builtupdated Apr 2024Oct 2023granted Apr 2024Apr 2024
Dykes Of Gray Roadsolar farmsolar farm2approved, not built may be out of dateupdated May 2024Sep 2021granted Mar 2022May 2024
The James Hutton Institutesolar farmsolar farm2approved, not built may be out of dateupdated May 2024Oct 2021granted Jan 2022May 2024
Findony Farm, Dunningsolar farmsolar farm2approved, not built may be out of dateupdated Jan 2023Nov 2022granted Jan 2023Jan 2023
Aviva Headquarterssolar farmsolar farm1.8operationalupdated Nov 2020Jun 2019granted Jul 2019Nov 2020
Pitheavliswind turbinewind turbine1approved, not builtupdated Mar 2022Mar 2022granted Oct 2022Mar 2022
West of Hallhole Farm, Meikleourwind turbinewind turbine1approved, not builtupdated Jan 2026Jun 2024granted Dec 2025Jan 2026
Smaller schemes under 1 MW, mostly rooftop solar (13)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
East Gormack Farmsolar farmsolar farm0.8approved, not built may be out of dateupdated Jun 2023Jan 2023granted May 2023Jun 2023
Perth Wastewater Treatment Workssolar farmsolar farm0.4operationalupdated Apr 2023Feb 2019granted Jun 2019Apr 2023
Perth Wastewater Treatment Works (Extension)solar farmsolar farm0.3operationalupdated May 2021May 2020granted Sep 2020May 2021
Killiecrankie Waste Water Treatment Worksrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Jan 2023Dec 2022granted Jan 2023Jan 2023
Burnside Farm, Stanley Solar Farmsolar farmsolar farm0.2approved, not built may be out of dateupdated Jun 2023Mar 2023granted Jun 2023Jun 2023
Blair Castle Caravan Park, Blair Atholl Solar Farmsolar farmsolar farm0.2operationalupdated Jul 2023Jun 2023granted Jul 2023Jul 2023
Perth Wastewater Treatment Works (Extension)battery storagebattery storage—operationalupdated Jan 2022May 2020granted Sep 2020Jan 2022
Rowan Gate Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated Aug 2025Apr 2022granted Jul 2022Aug 2025
East Gormack Farmbattery storagebattery storage—approved, not built may be out of dateupdated Jun 2023Jan 2023granted May 2023Jun 2023
Waste Water Treatment Works, Almondbank - Pumping Station & Solar Panelssolar farmsolar farm—approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023
Kinnon Park Farm, Methven Solar Farm & Battery Storagebattery storagebattery storage—refusedupdated Jun 2026Sep 2024refused May 2026Jun 2026
Kanthal, Ruthvenfield Roadrooftop solarrooftop solar—application submittedupdated Jul 2025Jun 2025—Jul 2025
Wind Farm at Meall Dearg Wind Farmbattery storagebattery storage—application submittedupdated Oct 2025Aug 2025—Oct 2025

Postcode districts in Perth and Kinross

DistrictProjects within 10 kmPendingApprovedOperational
KY1313150
PH118554
PH231787
PH312051
PH415065
PH56040
PH62010
PH74010
PH83001
PH91001
PH1018184
PH1112143
PH1217283
PH1318192
PH1412061
PH153001
PH163012
PH172000
PH182011

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Perth and Kinross by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.