Solar, wind and battery projects near Comrie (PH6)
2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PH6 (Perth and Kinross): 1 approved but not yet running. The largest live scheme is Strathallan Wind Farm (20.7 MW wind farm, under construction since 1 February 2023), 9.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PH6
Projects of 1 MW and more (2)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Abercairneywind farm | wind farm | 66 | refused on appealupdated Jan 2010 | Jan 2004 | refused Oct 2006 | Jan 2010 | Perth and Kinross | 9.0 |
| Strathallan Wind Farmwind farm | wind farm | 20.7 | under constructionupdated Feb 2023 | Oct 2015 | granted Jan 2019 | Feb 2023 | Perth and Kinross | 9.6 |
Distance from the average position of the PH6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Wind farm | 2 | 0 | 1 | 0 | 1 | 20.7 |
MW in pipeline: pending, approved and under-construction capacity.
How Perth and Kinross decides solar, wind and battery applications
| Applications | Perth and Kinross | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 73 | 10,236 |
| Refused | 32 (44%) | 19% |
| Solar refused | 6 of 24 | 12% |
| Onshore wind refused | 23 of 31 | 45% |
| Battery storage refused | 3 of 18 | 16% |
| Median time from submission to decision | 28.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 8 | — |
All projects in Perth and Kinross
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.