Strathallan Wind Farm (20.7 MW)

Strathallan Wind Farm is a 20.7 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 February 2023; the record was last updated on 20 February 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.7 MWwind farm
under constructionstatus in REPD
20 February 2023record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
12 October 2015Application submitted
12 April 2017Refused by the planning authority
7 July 2017Appeal lodged
15 January 2019Planning permission granted
15 January 2019Appeal allowed
1 February 2023Construction started

Project details

Technology
wind farm
Capacity
20.7 MW
Status (REPD)
under construction
Record last updated
20 February 2023
Operator or applicant
Green Cat Renewables
Planning authority
Perth and Kinross
Planning application reference
15/01484/FLM
Appeal reference
PPA-340-2110
Turbines
9
Turbine height
93 m
Address (REPD)
Ld 900 Metres NE Of Greenacres, Braco, Strathallan Wind Farm, Dunblane
Council area (by location)
Perth and Kinross
Time to decision
170 weeks
REPD reference
2860

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Shindour Energy Storage Facilitybattery storage49.9approved, not built3.8
Shindour, Feddal Hill Woodbattery storage50approved, not built3.8
Shindour Feddal Hill Wood Bracobattery storage10abandoned4.1
Standingfauld Farmwind farm20refused on appeal5.7
Standingfauld Farm, Muthillsolar farm14approved, not built6.0
Braes O'Dounewind farm72operational8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2962, -3.9239).