Energy Projects Near You

Solar, wind and battery projects near Muthill (PH5)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PH5 (Perth and Kinross): 4 approved but not yet running. The largest live scheme is Strathallan Wind Farm (20.7 MW wind farm, under construction since 1 February 2023), 6.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
4approved, not running
0operational

Projects within 10 km of PH5

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Standingfauld Farm, Muthillsolar farmsolar farm14approved, not built may be out of dateupdated Feb 2023Aug 2022granted Nov 2022Feb 2023Perth and Kinross3.0
Standingfauld Farmwind farmwind farm20refused on appealupdated Jan 2012Dec 2009refused May 2011Jan 2012Perth and Kinross3.2
Strathallan Wind Farmwind farmwind farm20.7under constructionupdated Feb 2023Oct 2015granted Jan 2019Feb 2023Perth and Kinross6.8
Rowan Gate Solar Farmsolar farmsolar farm7approved, not built may be out of dateupdated Aug 2025Apr 2022granted Jul 2022Aug 2025Perth and Kinross9.1
Shindour Feddal Hill Wood Bracobattery storagebattery storage10abandonedupdated Jan 2023Oct 2017—Jan 2023Perth and Kinross9.6
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rowan Gate Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated Aug 2025Apr 2022granted Jul 2022Aug 2025Perth and Kinross9.0

Distance from the average position of the PH5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2020021
Wind farm2010120.7
Battery storage201000

MW in pipeline: pending, approved and under-construction capacity.

How Perth and Kinross decides solar, wind and battery applications

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

All projects in Perth and Kinross

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PH5, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.