Solar, wind and battery projects near Crieff (PH7)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PH7 (Perth and Kinross): 1 approved but not yet running. The largest live scheme is Standingfauld Farm, Muthill (14 MW solar farm, approved on 8 November 2022, not yet built; REPD status may be out of date), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of PH7

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Abercairneywind farmwind farm66refused on appealupdated Jan 2010Jan 2004refused Oct 2006Jan 2010Perth and Kinross6.4
Mull Hill Windfarmwind farmwind farm22.5refused on appealupdated Jun 2014Dec 2011refused May 2013Jun 2014Perth and Kinross6.8
Standingfauld Farm, Muthillsolar farmsolar farm14approved, not built may be out of dateupdated Feb 2023Aug 2022granted Nov 2022Feb 2023Perth and Kinross7.9
Standingfauld Farmwind farmwind farm20refused on appealupdated Jan 2012Dec 2009refused May 2011Jan 2012Perth and Kinross8.1

Distance from the average position of the PH7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1010014
Wind farm300030

MW in pipeline: pending, approved and under-construction capacity.

How Perth and Kinross decides solar, wind and battery applications

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

All projects in Perth and Kinross

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PH7, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.