Abercairney (66 MW wind farm)

Abercairney is a 66 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 9 September 2006; the record was last updated on 11 January 2010. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

66 MWwind farm
refused on appealstatus in REPD
11 January 2010record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
9 January 2004Application submitted
9 September 2006Appeal refused
5 October 2006Refused by the planning authority

Project details

Technology
wind farm
Capacity
66 MW
Status (REPD)
refused on appeal
Record last updated
11 January 2010
Operator or applicant
Catamount Energy Ltd c/o Force 9
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
24
Address (REPD)
Nr Crieff, Gilmerton
Council area (by location)
Perth and Kinross
Time to decision
143 weeks
REPD reference
3227

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Mull Hill Windfarmwind farm22.5refused on appeal4.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.4216, -3.8841).