Mull Hill Windfarm (22.5 MW)
Mull Hill Windfarm is a 22.5 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 23 April 2014; the record was last updated on 2 June 2014.
22.5 MWwind farm
refused on appealstatus in REPD
2 June 2014record last updated
Perth and Kinrosscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 23 December 2011 | Application submitted |
| 23 May 2013 | Refused by the planning authority |
| 23 April 2014 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 22.5 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 2 June 2014
- Operator or applicant
- Force 9 Energy
- Planning authority
- Perth and Kinross
- Planning application reference
- 11/02151/FLM
- Appeal reference
- 13/00010/REF
- Turbines
- 9
- Address (REPD)
- Mull Hill, Meall Tarsuinn, Nr Monzie
- Council area (by location)
- Perth and Kinross
- Time to decision
- 74 weeks
- REPD reference
- 3866
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Pentre Tump RAD/2002/0397 | 9.2 | 11 September 2002 | refused 17 February 2010 |
Who decides
| Applications | Perth and Kinross | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 73 | 10,236 |
| Refused | 32 (44%) | 19% |
| Solar refused | 6 of 24 | 12% |
| Onshore wind refused | 23 of 31 | 45% |
| Battery storage refused | 3 of 18 | 16% |
| Median time from submission to decision | 28.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 8 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Abercairney | wind farm | 66 | refused on appeal | 4.5 |
| Parks of Kellour Wind Farm | wind farm | 12 | refused | 9.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.433, -3.8134).