Mull Hill Windfarm (22.5 MW)

Mull Hill Windfarm is a 22.5 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 23 April 2014; the record was last updated on 2 June 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22.5 MWwind farm
refused on appealstatus in REPD
2 June 2014record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
23 December 2011Application submitted
23 May 2013Refused by the planning authority
23 April 2014Appeal refused

Project details

Technology
wind farm
Capacity
22.5 MW
Status (REPD)
refused on appeal
Record last updated
2 June 2014
Operator or applicant
Force 9 Energy
Planning authority
Perth and Kinross
Planning application reference
11/02151/FLM
Appeal reference
13/00010/REF
Turbines
9
Address (REPD)
Mull Hill, Meall Tarsuinn, Nr Monzie
Council area (by location)
Perth and Kinross
Time to decision
74 weeks
REPD reference
3866

Earlier applications for this site

ApplicationMWSubmittedOutcome
Pentre Tump RAD/2002/03979.211 September 2002refused 17 February 2010

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Abercairneywind farm66refused on appeal4.5
Parks of Kellour Wind Farmwind farm12refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.433, -3.8134).