Energy Projects Near You

Solar, wind and battery projects near Dunblane (FK15)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of FK15 (Stirling): 1 is waiting for a planning decision, 6 approved but not yet running, 1 operational. The largest live scheme is Shindour, Feddal Hill Wood (50 MW battery storage, approved on 24 October 2024, not yet built), 6.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
1awaiting a decision
6approved, not running
1operational

Projects within 10 km of FK15

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Shindour Feddal Hill Wood Bracobattery storagebattery storage10abandonedupdated Jan 2023Oct 2017—Jan 2023Perth and Kinross6.5
Shindour, Feddal Hill Woodbattery storagebattery storage50approved, not builtupdated Jan 2025Jan 2023granted Oct 2024Jan 2025Perth and Kinross6.7
Shindour Energy Storage Facilitybattery storagebattery storage49.9approved, not built may be out of dateupdated Feb 2025May 2021granted Dec 2021Feb 2025Perth and Kinross6.7
Manor Powissolar farmsolar farm5application withdrawnupdated Jul 2017Jul 2016—Jul 2017Stirling8.6
Easter Cringate Cottage, Polmaise Roadwind farmwind farm30application submittedupdated Sep 2024Aug 2024—Sep 2024Stirling9.5
Forthside Way Battery Storage Unitbattery storagebattery storage1approved, not built may be out of dateupdated Jan 2022Nov 2021granted Dec 2021Jan 2022Stirling9.7
Unit 15, Borrowmeadow Roadbattery storagebattery storage19abandonedupdated Nov 2019Aug 2017—Nov 2019Stirling9.8
Braes O'Dounewind farmwind farm72operationalupdated Jan 2015Oct 2002granted Oct 2004Jan 2015—10.0
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
University Of Stirling, Airthrey Roadrooftop solarrooftop solar0.3approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024Stirling6.2
Cottrell Building, East Link Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2024Jun 2024granted Aug 2024Sep 2024Stirling6.7
Airthrey Road PV Solar Panelsrooftop solarrooftop solar—approved, not built may be out of dateupdated Feb 2022Dec 2021granted Feb 2022Feb 2022Stirling7.1

Distance from the average position of the FK15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100000
Rooftop solar303000.8
Wind farm2101030
Battery storage50300101

MW in pipeline: pending, approved and under-construction capacity.

How Stirling decides solar, wind and battery applications

ApplicationsStirlingUK
Decided applications (solar, wind, battery)2310,236
Refused7 (30%)19%
Solar refused0 of 712%
Onshore wind refused6 of 1145%
Battery storage refused1 of 516%
Median time from submission to decision30.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

All projects in Stirling

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near FK15, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.