Energy Projects Near You

Solar, wind and battery projects near Menstrie (FK11)

24 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of FK11 (Clackmannanshire): 3 are waiting for a planning decision, 11 approved but not yet running, 5 operational. The largest live scheme is Devilla Energy Storage Facility (500 MW battery storage, under construction since 1 March 2025), 4.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24projects within 10 km
3awaiting a decision
11approved, not running
5operational

Projects within 10 km of FK11

Projects of 1 MW and more (20)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Manor Powissolar farmsolar farm5application withdrawnupdated Jul 2017Jul 2016—Jul 2017Stirling2.9
Farm at Lower Polmaisesolar farmsolar farm5permission expiredupdated Oct 2019Sep 2015granted Oct 2015Oct 2019Stirling4.0
Windburn Wind Farmwind farmwind farm65application submittedupdated Aug 2025Jun 2025—Aug 2025Clackmannanshire4.0
Windburn Wind Farmbattery storagebattery storage35application submittedupdated Aug 2025Jun 2025—Aug 2025Clackmannanshire4.0
Bankhead Farmbattery storagebattery storage25approved, not builtupdated May 2024Jan 2024granted May 2024May 2024Clackmannanshire4.7
Devilla Energy Storage Facilitybattery storagebattery storage500under constructionupdated Oct 2025Apr 2022granted Dec 2023Oct 2025Clackmannanshire4.7
Forthside Way Battery Storage Unitbattery storagebattery storage1approved, not built may be out of dateupdated Jan 2022Nov 2021granted Dec 2021Jan 2022Stirling5.2
Unit 15, Borrowmeadow Roadbattery storagebattery storage19abandonedupdated Nov 2019Aug 2017—Nov 2019Stirling5.3
Easter Cringate Cottage, Polmaise Roadwind farmwind farm30application submittedupdated Sep 2024Aug 2024—Sep 2024Stirling6.3
Shelloch Wind Farmwind farmwind farm24approved, not builtupdated Aug 2025Jan 2021granted Feb 2022Aug 2025Stirling7.1
Rhodders Wind Farmwind farmwind farm12operationalupdated Feb 2016Nov 2011granted Jan 2014Feb 2016Perth and Kinross7.4
Forthbankwind farmwind farm5refusedupdated Nov 2012Nov 2010refused Oct 2012Nov 2012Falkirk7.4
Earlsburn Wind Farm Extensionwind farmwind farm34approved, not builtupdated Jan 2026Dec 2022granted Dec 2025Jan 2026Stirling8.1
Earlsburn Wind Farm Extensionbattery storagebattery storage18approved, not builtupdated Jan 2026Dec 2022granted Dec 2025Jan 2026Stirling8.1
Burnfoot Hillwind farmwind farm26operationalupdated Nov 2010Mar 2006granted Mar 2007Nov 2010Perth and Kinross8.2
Balhearty Solarsolar farmsolar farm5operationalupdated Jul 2018Oct 2015granted Dec 2015Jul 2018Clackmannanshire8.7
Burnfoot East Wind Farm (further extension)wind farmwind farm10.8operationalupdated Feb 2024Jan 2017granted Mar 2019Feb 2024Perth and Kinross8.7
Burnfoot Hill Extensionwind farmwind farm4operationalupdated Sep 2014Dec 2011granted Apr 2013Sep 2014Perth and Kinross8.9
Pirnhall Services, Bannockburn Interchangesolar farmsolar farm4approved, not builtupdated Jul 2025May 2024granted May 2025Jul 2025Stirling9.3
Frandy Hillwind farmwind farm14refused on appealupdated Nov 2013Dec 2011refused Apr 2013Nov 2013Perth and Kinross10.0
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cottrell Building, East Link Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2024Jun 2024granted Aug 2024Sep 2024Stirling4.3
University Of Stirling, Airthrey Roadrooftop solarrooftop solar0.3approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024Stirling4.6
Airthrey Road PV Solar Panelsrooftop solarrooftop solar—approved, not built may be out of dateupdated Feb 2022Dec 2021granted Feb 2022Feb 2022Stirling4.8
Alloa Wastewater Treatment Works, Bowhouse Roadsolar farmsolar farm0.9approved, not built may be out of dateupdated Jul 2023Mar 2023granted Jul 2023Jul 2023Clackmannanshire6.1

Distance from the average position of the FK11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm502105
Rooftop solar303000.8
Wind farm102242153
Battery storage61400579

MW in pipeline: pending, approved and under-construction capacity.

How Clackmannanshire decides solar, wind and battery applications

Clackmannanshire has 7 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Clackmannanshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near FK11, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.