Burnfoot Hill (26 MW wind farm)

Burnfoot Hill is a 26 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 October 2010; the record was last updated on 3 November 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26 MWwind farm
operationalstatus in REPD
3 November 2010record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
20 March 2006Application submitted
28 March 2007Planning permission granted
1 August 2010Construction started
26 October 2010Operational

Project details

Technology
wind farm
Capacity
26 MW
Status (REPD)
operational
Record last updated
3 November 2010
Operator or applicant
EDF Energies Nouvelles
Planning authority
Clackmannanshire
Planning application reference
06/00121/FULL
Turbines
13
Address (REPD)
Burnfoot Hill, Clackmannanshire
Council area (by location)
Perth and Kinross
Time to decision
53 weeks
REPD reference
2902

Who decides

Clackmannanshire has 7 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Burnfoot East Wind Farm (further extension)wind farm10.8operational0.8
Rhodders Wind Farmwind farm12operational0.8
Frandy Hillwind farm14refused on appeal2.4
Rowan Gate Solar Farmsolar farm7approved, not built5.2
Windburn Wind Farmwind farm65application submitted6.6
Bankhead Farmbattery storage25approved, not built7.4
Green Knoweswind farm27operational8.0
Balhearty Solarsolar farm5operational8.3
Green knowes Windfarm Ext.wind farm10application withdrawn8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2091, -3.7728).