Green Knowes (27 MW wind farm)

Green Knowes is a 27 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 September 2008; the record was last updated on 10 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWwind farm
operationalstatus in REPD
10 May 2016record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
4 August 2004Application submitted
15 June 2006Refused by the planning authority
13 June 2008Planning permission granted
13 June 2008Appeal allowed
14 June 2008Construction started
29 September 2008Operational

Project details

Technology
wind farm
Capacity
27 MW
Status (REPD)
operational
Record last updated
10 May 2016
Operator or applicant
CRE Energy/ Scottish Power
Planning authority
Perth and Kinross
Planning application reference
04/01651/FUL
Turbines
18
Address (REPD)
Land at Green Knowes, by Glendevon
Council area (by location)
Perth and Kinross
Time to decision
201 weeks
REPD reference
3487

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Green knowes Windfarm Ext.wind farm10application withdrawn1.5
Little Law Wind Farmwind farm27refused on appeal3.4
Snowgoat Glen Wind Farmwind farm23.5application withdrawn4.7
Snowgoat Glen Wind Farm IIwind farm13refused4.7
Earnieside Farmhouse, Dunning Glen Wind Farmwind farm48approved, not built4.9
Mellock Hill Wind Farmwind farm48refused5.7
Mellock Hill Wind Farm IIwind farm35application withdrawn5.7
Rowan Gate Solar Farmsolar farm7approved, not built5.9
Frandy Hillwind farm14refused on appeal5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2492, -3.6663).