Little Law Wind Farm (27 MW)

Little Law Wind Farm is a 27 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 8 August 2007; the record was last updated on 2 December 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWwind farm
refused on appealstatus in REPD
2 December 2014record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
18 June 2004Application submitted
22 June 2005Refused by the planning authority
21 December 2005Appeal lodged
8 August 2007Appeal refused

Project details

Technology
wind farm
Capacity
27 MW
Status (REPD)
refused on appeal
Record last updated
2 December 2014
Operator or applicant
Green Power International
Planning authority
Perth and Kinross
Planning application reference
04/01321/FUL
Appeal reference
PPA-340-484
Turbines
18
Address (REPD)
Auchterarder, Perthshire
Council area (by location)
Perth and Kinross
Time to decision
53 weeks
REPD reference
3526

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Snowgoat Glen Wind Farm IIwind farm13refused1.5
Snowgoat Glen Wind Farmwind farm23.5application withdrawn1.5
Green knowes Windfarm Ext.wind farm10application withdrawn3.2
Green Knoweswind farm27operational3.4
Mellock Hill Wind Farmwind farm48refused3.6
Mellock Hill Wind Farm IIwind farm35application withdrawn3.6
Earnieside Farmhouse, Dunning Glen Wind Farmwind farm48approved, not built4.4
Knowes Farmwind farm7.7refused4.9
Rowan Gate Solar Farmsolar farm7approved, not built9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2634, -3.6168).