Green knowes Windfarm Ext. (10 MW)
Green knowes Windfarm Ext. is a 10 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 30 March 2017; the record was last updated on 31 March 2017.
10 MWwind farm
application withdrawnstatus in REPD
31 March 2017record last updated
Perth and Kinrosscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 21 December 2015 | Application submitted |
| 30 March 2017 | Application withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 10 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 31 March 2017
- Operator or applicant
- Scottish Power Renewables
- Planning authority
- Perth and Kinross
- Planning application reference
- 15/02197/FLL
- Turbines
- 5
- Turbine height
- 111 m
- Address (REPD)
- Greenknowes Windfarm, Glendevon, Dollar
- Council area (by location)
- Perth and Kinross
- REPD reference
- 4810
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Green Knowes Extension 05/01061/FUL | 31.5 | 31 May 2005 | refused 6 December 2005 |
Who decides
| Applications | Perth and Kinross | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 73 | 10,236 |
| Refused | 32 (44%) | 19% |
| Solar refused | 6 of 24 | 12% |
| Onshore wind refused | 23 of 31 | 45% |
| Battery storage refused | 3 of 18 | 16% |
| Median time from submission to decision | 28.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 8 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Green Knowes | wind farm | 27 | operational | 1.5 |
| Little Law Wind Farm | wind farm | 27 | refused on appeal | 3.2 |
| Earnieside Farmhouse, Dunning Glen Wind Farm | wind farm | 48 | approved, not built | 3.4 |
| Mellock Hill Wind Farm II | wind farm | 35 | application withdrawn | 4.5 |
| Mellock Hill Wind Farm | wind farm | 48 | refused | 4.5 |
| Snowgoat Glen Wind Farm | wind farm | 23.5 | application withdrawn | 4.7 |
| Snowgoat Glen Wind Farm II | wind farm | 13 | refused | 4.7 |
| Frandy Hill | wind farm | 14 | refused on appeal | 6.3 |
| Rowan Gate Solar Farm | solar farm | 7 | approved, not built | 7.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2405, -3.6475).