Snowgoat Glen Wind Farm (23.5 MW)

Snowgoat Glen Wind Farm is a 23.5 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 26 May 2006; the record was last updated on 26 May 2006.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

23.5 MWwind farm
application withdrawnstatus in REPD
26 May 2006record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
5 July 2004Application submitted
26 May 2006Application withdrawn

Project details

Technology
wind farm
Capacity
23.5 MW
Status (REPD)
application withdrawn
Record last updated
26 May 2006
Operator or applicant
RWE npower
Planning authority
Perth and Kinross
Planning application reference
04/01049/FUL
Address (REPD)
Near Dunning Perth and Kinross
Council area (by location)
Perth and Kinross
REPD reference
3283

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Snowgoat Glen Wind Farm IIwind farm13refused<0.1
Little Law Wind Farmwind farm27refused on appeal1.5
Knowes Farmwind farm7.7refused3.4
Mellock Hill Wind Farm IIwind farm35application withdrawn4.5
Mellock Hill Wind Farmwind farm48refused4.5
Green knowes Windfarm Ext.wind farm10application withdrawn4.7
Green Knoweswind farm27operational4.7
Earnieside Farmhouse, Dunning Glen Wind Farmwind farm48approved, not built5.7
Shire-End Farmsolar farm17approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2765, -3.6085).