Snowgoat Glen Wind Farm II (13 MW)

Snowgoat Glen Wind Farm II is a 13 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 30 November 2005; the record was last updated on 26 May 2006.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13 MWwind farm
refusedstatus in REPD
26 May 2006record last updated
Perth and Kinrosscouncil area

Planning timeline

DateStage
1 June 2005Application submitted
30 November 2005Refused by the planning authority

Project details

Technology
wind farm
Capacity
13 MW
Status (REPD)
refused
Record last updated
26 May 2006
Operator or applicant
RWE npower
Planning authority
Perth and Kinross
Planning application reference
05/01043
Turbines
10
Address (REPD)
Near Dunning Perth and Kinross
Council area (by location)
Perth and Kinross
Time to decision
26 weeks
REPD reference
3273

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Snowgoat Glen Wind Farmwind farm23.5application withdrawn<0.1
Little Law Wind Farmwind farm27refused on appeal1.5
Knowes Farmwind farm7.7refused3.4
Mellock Hill Wind Farm IIwind farm35application withdrawn4.5
Mellock Hill Wind Farmwind farm48refused4.5
Green knowes Windfarm Ext.wind farm10application withdrawn4.7
Green Knoweswind farm27operational4.7
Earnieside Farmhouse, Dunning Glen Wind Farmwind farm48approved, not built5.7
Shire-End Farmsolar farm17approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2765, -3.6085).